DART test trains up and running
Tests will be conducted on an almost daily basis until the section opens September 14. The tests are designed to evaluate the operation of the new light rail track and to familiarize rail operators with the operating characteristics of the trains on the new line.

With fewer than 100 days before it opens, Dallas Area Rapid Transit (DART) is conducting train tests along the 2.7-mile Green Line light rail corridor between the Pearl Station and MLK Jr. Station near Fair Park.
The tests will be conducted on an almost daily basis until the section opens September 14. The tests are designed to evaluate the operation of the new light rail track and to familiarize rail operators with the operating characteristics of the trains on the new line.
The Green Line marks the return of rail service to some neighborhoods after a 50-year absence, so the agency is urging motorists to remember to look for trains. Major train crossings on the corridor are clearly marked with signs, red flashing lights and crossing arms that come down prior to the train’s arrival at the intersection. At other crossings DART trains will follow traffic signals.
Follow the progress of the Green Line at www.DART.org/constructionupdates.
More Rail

The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →
Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet
The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.
Read More →
When Routine Fails: How Public Transit Must Adapt for the World Cup
The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.
Read More →
California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract
The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.
Read More →
Seattle's Sound Transit Launches New Sounder Railcars into Service
Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.
Read More →
Alstom Partners With Universities to Build Rail Talent Pipeline
The partnerships include a new engineering scholarship fund at Alfred State College in Western New York and collaborations with transportation centers at the University of Pennsylvania and New York University.
Read More →
Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin
Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.
Read More →
Seattle’s Sound Transit Adopts Updated ST3 System Plan
The updated system plan incorporates cost savings across the agency, including new revenue sources and financial policies, to set the agency on a sustainable path for the future.
Read More →
Inside Look: EMBARK Expands Fare-Free Transit Program Through New Public-Private Partnership
The OKC transit agency says sponsorship helps subsidize the Third Friday Free initiative while reducing barriers for first-time riders and boosting ridership across buses, streetcars, and river cruises.
Read More →