Judge's decision to bolster Calif. high-speed rail project

The judgment means bidding and construction will move ahead as planned on the first phase of the 800-mile high-speed rail system set to connect the northern and southern parts of the state.

Nicole Schlosser
Nicole SchlosserFormer Executive Editor
January 8, 2013
Judge's decision to bolster Calif. high-speed rail project

 

4 min to read


In November, Sacramento County Superior Court Judge Timothy Frawley made a preliminary ruling to reject a bid by agricultural interests to temporarily stop California’s high-speed rail project in the Central Valley until a lawsuit can be decided.

The judgment means bidding and construction will move ahead as planned on the first phase of the 800-mile high-speed rail system set to connect the northern and southern parts of the state.

Ad Loading...

At press time, a final ruling was not announced but it is not expected to change, Rod Diridon, head of the Mineta Transportation Institute at San Jose State University, said.

Judge Frawley ruled that the cost of delaying the project outweighed the risk to farmers and others along the route whose property would be affected. The judge also said it was not clear to him at this point that the authority had failed to meet the standards of the environmental quality act, which was the premise of the lawsuit.

Meanwhile, additional factors, such as President Barack Obama’s re-election, Gov. Jerry Brown’s signing of a bill authorizing the sale of bonds for the project and a Democrat majority in the state legislature, has spurred support for high-speed rail in California.

“The president touted high-speed rail as part of his campaign platform. That [could] be a referendum on high-speed rail nationally,” Diridon said. “Certainly the judge’s ruling is an element of that.”

Currently, project bids and RFPs are out for the first five contracts. These  entail rail from Chowchilla to South Fresno, including a complicated construction project with several undercrossings; preparing the road bed; rail from Fresno and Chowchilla to Bakersfield; and capping off the road bed and installing ties and rail at a standard that would support 220-mile per hour (mph) speeds.

Ad Loading...

The Central Valley was chosen as the project’s starting point based on strictures given by the state to the California High Speed Rail Authority (CaHSRA) in the mid-2000s. One required the line to be located between two large population centers — the Fresno metropolitan area now has nearly one million people and the Bakersfield metropolitan area is approaching 500,000 people. The other strictures required the maintenance base to be in the middle of the line, and for a section of track to be straight enough to test the rolling stock at maximum speed.

With those factors combined, and the fact that the area had the highest construction unemployment, nearing 30% in the state, CaHSRA adopted the idea of starting the system in the Central Valley.

The ruling may change the opinion of people who were doubtful the project could be completed because of issues such as the lawsuit.

Diridon said that among the three major positions on high-speed rail in the state, the largest group is comprised of people who want the system built immediately, no matter the cost, and the second group, made up of about 25% of Californians, is fundamentally opposed to spending money on the project.

However, the third group, which was uncertain, is shrinking as more positive information about the project comes out, Diridon said.
“The latest version of the business plan, which had been assailed for so many years as being too liberal, is now being recognized as being conservative and accurate by a conservative advisory group to the California High Speed Rail Authority, as well as many legislative review organiza-tions,” he added.

Ad Loading...

The next steps on the project are to open the bids, identify the preferred bidders, negotiate the details and begin the contracts. Construction of the first phase of the project is set to begin in July with the route between Merced and Fresno, an area in the central part of the state that consists primarily of farms.

The total project cost is expected to be $68 billion.

“We’re hoping that the president is able to create additional funding for high-speed rail, not just for California, but for the 12 other corridors in the nation,” Diridon said.

He added that as the project moves forward, the hope is that private investors will realize the potential for “big net positive cash flow” and be willing to build the rest of the system in return for the franchise fees and profits.

Subscribe to Our Newsletter

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →