The five-mile Orange Line extension from Belt Line Station to the newly rebuilt Terminal A at DFW will bring the longest light rail system in the U.S. to 90 miles.
Nicole Schlosser・Former Executive Editor
May 16, 2014
3 min to read
On Aug. 18, Dallas Area Rapid Transit Authority (DART) will join the ranks of transit systems with rail connections to major airports as it opens its Dallas/Fort Worth International Airport (DFW) station four months ahead of schedule and under budget.
The five-mile Orange Line extension from Belt Line Station to the newly rebuilt Terminal A at DFW will bring the longest light rail system in the U.S. to 90 miles.
When the DFW Airport Station opens, riders will only need to walk about 300 feet from the station to the terminal, making it convenient for people traveling to and from the Dallas/Fort Worth area as well as for people who work at or near the airport, DART President/Executive Director Gary Thomas said.
“Opening a project of this complexity early and under budget is a great testament to the work of our DART team and our colleagues at DFW Airport,” Thomas said. “Support from the Federal Transit Administration and Federal Aviation Administration (FAA) was also crucial to beating the targeted opening.”
When the DFW Airport Station opens, riders will only need to walk about 300 feet from the station to Terminal A, making it convenient for people traveling to and from the Dallas/Fort Worth area and those who work at or near the airport.
DART received a $5 million Transportation Investment Generating Economic Recovery grant as well as a $119 million Transportation Infrastructure Finance and Innovation Act loan for the rail extension to the station. The first section of the Orange Line received $61 million in American Recovery and Reinvestment Act funds.
DART initially planned to be finished with the station in December. However, as its project partner, DFW International Airport was building the station, and as the transit system handled the track work and catenary systems, they realized they were ahead of schedule. Together, they were able to pin down the opening date, allowing enough time to get all the required testing and integration completed in a timely manner and still have enough time for the training of DART’s operators.
Ad Loading...
Choosing an August opening date was particularly beneficial because that will make the station accessible before the State Fair of Texas, which starts in late September, and brings significantly high ridership, Thomas said. For example, over the last couple of years, the number of additional trips related to the fair was approximately 700,000 over a three-week period.
The project has also created about 60,000 jobs in and around DFW airport, from employees on airport property and businesses adjacent to it associated with hospitality, storage and logistics. The project created between 500 and 1,000 jobs not counting ancillary jobs, such as parts manufacturing, he added.
“All of those are solid employee bases, so I anticipate that this will be a well-used part of our system,” Thomas said. “I think that will only grow as time goes on.”
DART is currently projecting 1,200 trips per day going to the airport station, but Thomas said he can see that growing once more people become aware of the new station.
One challenge in completing the project was working with all the government entities that have control over the airport property.
Ad Loading...
“When you connect to the airport, you not only [work with] the FTA or Federal Railroad Administration, depending on your mode, you also have the FAA, and the U.S. Department of Homeland Security and the Transportation Security Administration,” Thomas explained.
However, he said the project has been a good team effort.
“It’s been fun to work on, and our partners at DFW have been great,” Thomas said.
Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.
The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.
Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.
The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.
Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.