Old San Francisco bus terminal meets wrecking ball

Posted on December 6, 2010

[IMAGE]Transbay-2.jpg[/IMAGE]San Francisco's Transbay Joint Powers Authority's (TJPA) demolition contractor Evans Brothers Inc. dropped the historic first wrecking ball on the front facade of the old Transbay Terminal building, marking the project's progress as it works toward removing the old bus terminal and ramps to make way for the new, multi-modal Transbay Transit Center.

The demolition of the Transbay Terminal is currently in the third of four phases of activity. Work to remove the eastern bus ramps has already been completed along with the removal of the main building's roof, portions of the walls, and bus levels along with the steel overpasses over both First and Fremont Streets. As part of the project's LEED efforts, more than 6,500 tons of concrete have been demolished and will be crushed and reused on site.

The wrecking ball is planned to remain in use for the next few months as the remainder of the old Terminal structure is removed. A Temporary Terminal located a few blocks away on Beale and Howard Streets will continue to serve bus operations until the new Transbay Transit Center opens its doors in 2017.

The Transit Center will serve 11 transportation systems — including California High Speed Rail — and up to 45 million passengers per year. The LEED Gold building will also feature large public art works as part of the building design and a 5.4 acre public rooftop park.

View comments or post a comment on this story. (0 Comments)

More News

Man charged with murder after stabbing Winnipeg Transit bus driver

The incident occurred at 2 a.m., when the driver pulled up to the last stop of his shift and asked the man to leave the bus. After a physical altercation, which ended up outside the bus, ensued, the driver was stabbed multiple times.

N.Y.'s NICE to add 33 New Flyer buses

Twenty-eight 40-foot buses will replace existing buses in the NICE fleet that have reached the end of their useful life, while five 60-foot buses will be used on the customer's new bus rapid transit line, scheduled to start service in 2017.

Nova Bus, ABB partner for electric bus, charger delivery to N. America

The ABB DC fast charger, with the associated systems, is based on the common interface, which allows charging stations and electrified buses from different manufacturers to be used together.

Proterra names Horton to CCO post

Will lead the end-to-end customer lifecycle as Proterra triples production and initiates large-scale deployments across North America.

Stertil-Koni adds new capabilities to transmission jack

The battery-operated jack can be charged overnight and used without cables. The pneumatic jack has an attached air hose to keep it working. Previously, transmission jacks were manually hand-pumped, much like a car jack.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close