September 9, 2011

MTA's Metro-North assessing flood damage of line

A team of engineers hired by the Metropolitan Transportation Authority's (MTA) Metro-North Railroad is inspecting and assessing the catastrophic flood damage to the Port Jervis Line. Meanwhile buses are providing alternative service for the 2,300 people who normally use the line each weekday.

Significant damage to the line identified last week following Hurricane Irene by an aerial inspection includes up to 40 washout locations, including three washouts each at least a thousand feet long near Sloatsburg, a 400-foot section of track washed out just south of Sloatsburg, significant damage to several railroad bridges and exposure of what had been a subterranean signal cable.

Following through on MTA Chairman Jay Walder's emergency powers invoked to expedite rebuilding the devastated line, work began last week on an on-the-ground assessment of damage from the storm and a final condition assessment report is expected by the end of the month.

AECOM began a conditions analysis of track and structures along 14 of the hardest hit miles of the right-of-way as well as a hydrology study of the area. Their sub-consultant, Systra, is assessing all railroad communications and signal systems, while M.G. McLaren will assess damage to the rail bridges in the affected area.

AECOM was issued a Notice to Proceed for emergency work, not-to exceed $500,000.

Metro-North is studying its options to improve service.

 

deli.cio.us digg it stumble upon newsvine
[ Request More Info about this product / service / company ]


E-NEWSLETTER

Receive the latest Metro E-Newsletters in your inbox!

Join the Metro E-Newsletters and receive the latest news in your e-mail inbox once a week. SIGN UP NOW!

View the latest eNews
Express Tuesday | Express Thursday | University Transit

White Papers

Factors in Transit Bus Ramp Slope and Wheelchair-Seated Passenger Safety Nearly 3 million U.S. adults are wheelchair or scooter users1, and as the population ages this number is expected to rise. Many wheelchair users rely upon public transportation to access work, medical care, school and social activities.

Mass Transit Capital Planning An overview of the world-class best practices for assessing, prioritizing, and funding capital projects to optimize resources and align with the organization’s most critical immediate and long-term goals.

The Benefits of Door-to-Door Service in ADA Complementary Paratransit Many U.S. transit agencies continue to struggle with the quality of ADA service, the costs, and the difficulties encountered in contracting the service, which is the method of choice for a significant majority of agencies. One of the most basic policy decisions an agency must make involves whether to provide door-to-door, or only curb-to-curb service.

More white papers


 
DIGITAL EDITION

The full contents of Metro Magazine on your computer! The digital edition is an exact replica of the print magazine with enhanced search, multimedia and hyperlink features. View the current issue