L.A. Metro expands rail testing ahead of launch

The additional train testing is needed along the entire line in an effort to test the operation of the trains and all train and signal systems for the Metro Expo Line. No date has been set for the opening of the line. Metro will select an opening date for the public once all systems and trains are thoroughly tested and operated.

December 5, 2011
L.A. Metro expands rail testing ahead of launch

 

2 min to read


The Los Angeles County Metropolitan Transportation Authority (Metro) will expand the operation of test trains along the Metro Expo Line corridor beginning this week, running trains on a schedule of every 12 minutes during the day to simulate regular mid-day service on the line once the system opens in early 2012.

The additional train testing is needed along the entire line in an effort to test the operation of the trains and all train and signal systems for the Metro Expo Line. No date has been set for the opening of the line. Metro will select an opening date for the public once all systems and trains are thoroughly tested and operated.

Ad Loading...

Phase I of the Metro Expo Line is a new $932 million, 8.6-mile light rail line under construction from downtown Los Angeles to Culver City. It will have 12 stations with two stations shared with the Metro Blue Line. The new light rail line will serve USC, Exposition Park, The Mid-City communities, the Crenshaw District and Culver City.

Phase II of the Metro Expo Line, a $1.5 billion 6.6-mile extension from Culver City to Santa Monica, is funded under the Measure R half-cent sale tax initiative approved by the voters in 2008. Phase II will have seven stations serving West Los Angeles/Santa Monica and is expected to be completed in 2015.

Both Phase I and II of the Metro Expo Line are being built by the Expo Construction Authority. Once completed, they are turned over to Metro to operate.

 

More Rail

A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →
Alstom purchasing site for Acela network manufacturing
Railby StaffJune 4, 2026

Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet

The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.

Read More →
World Cup Crowds Will Test Transit Systems
ManagementJune 3, 2026

When Routine Fails: How Public Transit Must Adapt for the World Cup

The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.

Read More →
Ad Loading...
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 2, 2026

California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract

The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.

Read More →
Sound Transit Sounder train
Railby StaffJune 2, 2026

Seattle's Sound Transit Launches New Sounder Railcars into Service

Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.

Read More →
Railby StaffJune 2, 2026

Alstom Partners With Universities to Build Rail Talent Pipeline

The partnerships include a new engineering scholarship fund at Alfred State College in Western New York and collaborations with transportation centers at the University of Pennsylvania and New York University.

Read More →
Ad Loading...
Managementby StaffJune 1, 2026

Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin

Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.

Read More →