January 17, 2012

NYCT completes rail work via service initiative

For four consecutive weeknights hundreds of Metropolitan Transportation Authority New York City Transit (NYCT) workers labored through the late night and early morning hours cleaning, inspecting, repairing and replacing subway infrastructure on a nearly seven-mile segment of the normally busy Lexington Avenue Line.

NYCT's new FASTRACK initiative is an entirely new way to perform subway maintenance completely suspending train service over a segment of a subway line, giving workers uninterrupted access to tracks, signals, cables, lighting, third rail components and platform edges. During the four-night period, more than 300 vital tasks were completed — from rail replacement to roadbed cleaning to the scraping and painting of ceilings over tracks and platforms. Much of this work had not been performed in several years and some of it could only be done in the absence of trains over an extended period of time.

Three work trains supported nearly 70 work crews from several divisions within the Department of Subways. Work was performed in the stations along the line segment as well as the tunnels and even into the Joralemon Tube that connects Brooklyn to Manhattan.

In the planning for upwards of three months, the result was a seamless effort that saw maintenance workers specializing in different disciplines working to complete jobs and make improvements that customers would notice by the time service was resumed on the 4, 5 and 6 line for the next morning's rush period. Workers cleaned and replaced lighting fixtures, scraped dry mud from the roadbed while also removing trash and debris, as well as inspected and performed preventative maintenance on components crucial to providing safe and reliable service. They also scraped peeling paint from station ceilings and painted station areas. Rails were replaced in several areas along with a heavily utilized track switch just north of the Brooklyn Bridge Station.

Work also included inspections of equipment along the tracks; scraping and bagging of debris; replacement of tie and rail fastener plates; scraping and painting rubbing board and columns within station limits; cleaning of stations (mobile wash); cleaning of drains; and routine maintenance and performance testing of signals. All work was wrapped up and service restored to customers by 5:00 a.m. each morning.

deli.cio.us digg it stumble upon newsvine
[ Request More Info about this product / service / company ]


E-NEWSLETTER

Receive the latest Metro E-Newsletters in your inbox!

Join the Metro E-Newsletters and receive the latest news in your e-mail inbox once a week. SIGN UP NOW!

View the latest eNews
Express Tuesday | Express Thursday | University Transit

White Papers

Factors in Transit Bus Ramp Slope and Wheelchair-Seated Passenger Safety Nearly 3 million U.S. adults are wheelchair or scooter users1, and as the population ages this number is expected to rise. Many wheelchair users rely upon public transportation to access work, medical care, school and social activities.

Mass Transit Capital Planning An overview of the world-class best practices for assessing, prioritizing, and funding capital projects to optimize resources and align with the organization’s most critical immediate and long-term goals.

The Benefits of Door-to-Door Service in ADA Complementary Paratransit Many U.S. transit agencies continue to struggle with the quality of ADA service, the costs, and the difficulties encountered in contracting the service, which is the method of choice for a significant majority of agencies. One of the most basic policy decisions an agency must make involves whether to provide door-to-door, or only curb-to-curb service.

More white papers


 
DIGITAL EDITION

The full contents of Metro Magazine on your computer! The digital edition is an exact replica of the print magazine with enhanced search, multimedia and hyperlink features. View the current issue