NTSB issues Metro North derailment investigation update

The investigative group focusing on the track has learned from inspection reports that in April, maintenance work was done in the area of the derailment of the eastbound train. Records revealed that a joint bar, used to join two sections of rail together, was cracked and that it was repaired by Metro-North personnel.

May 24, 2013
2 min to read


The National Transportation Safety Board’s (NTSB) go-team departed Bridgeport, Conn., on Thursday after completing the on-scene phase of the investigation into the May 17 derailment and collision of two Metro-North trains and will now begin to analyze the information gathered.

NTSB investigators have collected photos, video, data, reports and records, and other evidence; completed mechanical inspections of the railcars, the track and signal system; interviewed several Metro-North employees, witnesses and first responders; and thoroughly documented the accident site.

The investigative group focusing on the track has learned from inspection reports that in April, maintenance work was done in the area of the derailment of the eastbound train. The records revealed that a joint bar, used to join two sections of rail together, was cracked and that it was repaired by Metro-North personnel. Sections of rail in the area of the derailment have been removed and shipped to the NTSB materials laboratory in Washington, D.C. for further examination. In addition, Metro-North is conducting an inspection and inventory of all the joint bars on its main line tracks.

Initial information obtained from onboard event recorders indicates that the eastbound train derailed, came to a stop, and was struck about 20 seconds later by the westbound train. With regard to the westbound train, information from the recorders indicates that the westbound train engineer applied the emergency brakes prior to striking the eastbound train.

During an interview with the eastbound train engineer, he informed NTSB investigators that he saw what he described as an unusual condition on the track as he approached the Interstate 95 overpass. He also stated that the train came to a stop before being struck by the westbound train.

The Metro-North trains involved in this accident were traveling on two separate but parallel tracks. The collision occurred after the eastbound train derailed. Because the trains were not traveling on a single track, it is not believed that positive train control would have prevented the accident.            

To read additional reporting from the AP, click here

More Management

New MobilityJune 5, 2026

Joshua Schank on Transportation Innovation, Risk, and the Future of Mobility

In this edition of METROspectives, Joshua Schank discusses lessons from launching LA Metro’s Office of Extraordinary Innovation, the challenges of advancing new mobility technologies, and much more.

Read More →
A maintenance person with a tablet.
ManagementJune 5, 2026

Reinventing Fleet Maintenance with Real-time Visibility and AI

Transit leaders need to know what needs fixing, where to look, who is responsible, when work is completed, and what it costs without having to chase information across disconnected systems.

Read More →
Alstom purchasing site for Acela network manufacturing
Railby StaffJune 4, 2026

Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet

The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.

Read More →
Ad Loading...
SamTrans planning for ballot measure
Managementby StaffJune 4, 2026

SamTrans Sets Priorities for Potential Connect Bay Area Revenue

The board-approved framework allocates future funding to maintaining service, rider improvements, equity initiatives, and infrastructure repairs.

Read More →
Riders in MARTA bus station
Security and Safetyby StaffJune 4, 2026

Federal Transit Officials Launch MARTA Safety Probe

FTA has given MARTA 15 days to provide records on crime prevention, fare evasion enforcement, and security funding as part of a broader safety investigation.

Read More →
ABA testifies for federal bus regulations

ABA's Ferguson Testifies in Support of BUS Act, National Standards for Bus Operators

The BUSES Act would create a nationwide framework preventing state and local governments from enforcing bus idling restrictions of less than 15 minutes, a threshold consistent with existing Environmental Protection Agency guidance.

Read More →
Ad Loading...
World Cup Crowds Will Test Transit Systems
ManagementJune 3, 2026

When Routine Fails: How Public Transit Must Adapt for the World Cup

The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.

Read More →
Jacksonville Transportation Authority America250 bus and transit van.
Managementby News/Media ReleaseJune 3, 2026

Florida’s JTA Puts Innovation in Motion Ahead of America250

The agency unveiled a commemorative America250 bus during a visit from U.S. DOT's Seval Oz and showcased its autonomous mobility programs.

Read More →
A rendering of a California High-Speed Rail vehicle
Railby StaffJune 2, 2026

California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract

The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.

Read More →
Ad Loading...
Technologyby StaffJune 2, 2026

IndyGo, Cleveland RTA Expand Digital Fare Payment Options with Masabi

The new systems combine mobile apps, smart cards, and automatic fare capping to simplify payments, expand flexibility, and help riders access the lowest available fares.

Read More →