MTA to close Sandy damaged tunnels for repairs
Temporary fixes brought those tunnels back into service, but the damage has led to increased failures of components, a growing number of delayed trains and a pressing need to make permanent repairs.

Montague Tube image courtesy MTA New York City Transit / Marc A. Hermann

Two New York subway tunnels heavily damaged by Hurricane Sandy will be closed for long-term repairs this summer, the Metropolitan Transportation Authority announced.
The Greenpoint Tube, which carries the G train under Newtown Creek between Brooklyn and Queens, will be closed for 12 weekends this summer and fall starting July 6. The Montague Tube, an almost mile-long pair of tunnels that carries the R train under the East River between Brooklyn and Manhattan, will be closed for up to 14 months starting the first week in August.
Sandy inundated the tubes with millions of gallons of seawater, which corroded, degraded, or ruined almost everything from tracks and switches, to signals and controls, to power and communications cables. Temporary fixes brought those tunnels back into service, but the damage has led to increased failures of components, a growing number of delayed trains and a pressing need to make permanent repairs.
In the Greenpoint Tube, power cables that were immersed in salt water are corroding from the inside, while corrosion on the outside of rails and fasteners raises the potential for short circuits. The controls for ventilation, lighting and communication systems were destroyed and have not been restored to their pre-Sandy condition.

The Montague Tube is in far worse condition and will require much more extensive repairs. It was flooded for a length of 4,025 feet to a depth of 20 feet with corrosive salt water sitting stagnant in the tube for 10 days. More than 27 million gallons of water were eventually pumped from the tube before work began to make it useable again for train service. While the work was enough to restore R service between Brooklyn Heights and Lower Manhattan, it was never intended to be a permanent repair.
VIDEO: Check out video of MTA officials inspecting the Montague Tube.
More Rail

Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →
Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet
The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.
Read More →
When Routine Fails: How Public Transit Must Adapt for the World Cup
The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.
Read More →
California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract
The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.
Read More →
Seattle's Sound Transit Launches New Sounder Railcars into Service
Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.
Read More →
Alstom Partners With Universities to Build Rail Talent Pipeline
The partnerships include a new engineering scholarship fund at Alfred State College in Western New York and collaborations with transportation centers at the University of Pennsylvania and New York University.
Read More →
Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin
Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.
Read More →