Dallas light rail opens on time, under budget

Posted on December 22, 2010 by Nicole Schlosser, Associate Editor - Also by this author

Page 1 of 2

[IMAGE]MET1news-DARTCarrolltonStation-2.jpg[/IMAGE]On Dec. 6, 2010 Dallas Area ­Rapid Transit (DART) marked the completion of its 28-mile, 20-station, $1.8 billion Green Line on schedule and under budget, when it opened 24 miles and 15 stations, creating new light rail connections for riders from southeast Dallas to the cities of Farmers Branch and Carrollton in the northwest.

The first section of the Green Line opened in September 2009 and connects Pearl Station on the east side of Downtown Dallas to MLK, Jr. Station on the west side of Fair Park.

"The Green Line makes our system a little more complete," DART President/Executive Director Gary Thomas said. "We had north, south, northeast and southwest covered but we didn't have northwest or southeast covered."                

The additional line offers connections to more destinations popular among riders. "Customers living in Pleasant Grove now have seamless access to jobs at Baylor University, Downtown Dallas, the Market District, University of Texas-Southwestern/Parkland, Love Field Airport and Farmers Branch and Carrollton," explained Thomas. "Business owners all along the corridor can connect with new customers and new pools of prospective employees."

While DART already had bus coverage in the transit corridors now served by the Green Line extension, the rail provides quicker, more dependable service, Thomas added. For example, customers of the Denton County Transportation Authority (DCTA) who have been riding an express bus to Downtown Dallas will be able to transfer to the Green Line at Trinity Mills Station. The DCTA's A-Train is scheduled to open in summer 2011.

The new stations also represent 15 additions to DART's growing public art collection. Each station is designed to reflect the surrounding community, giving each station a unique look. Community volunteers, DART staff and station artists worked together for months on the new stations. The art may be found in windscreens, landscaping and fences at Lawnview Station or, a signature piece, such as the wayfinder monument at the North Carrollton/Frankford Station.

View comments or post a comment on this story. (0 Comments)

More News

Metro-North employees commended for saving colleague’s life

Jeff Ballard, a Brewster Yardmaster took his colleague’s pulse and recognized that he was having a heart attack.

Dozens of teens storm BART train, rob passengers

The incident happened at 9:30 p.m. Saturday at the Coliseum Station in Oakland aboard a Dublin/Pleasanton-bound train.

Sunrail explores other modes for proposed airport link

The high cost of heavy commuter rail trains is the reason for the debate.

Alstom delivers first metro cars for additional Panama fleet

Alstom will also upgrade the existing signalling and power supply infrastructure, required to run the extended fleet with five cars per train.

New York MTA expects new subway cars to begin service this year

Originally expected to be delivered in 2014, the first car from manufacturers Bombardier Transportation didn’t arrive in New York until September of last year.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close