Rail

Calif.'s Metrolink weathers record storms, plans service upgrades

Posted on February 9, 2011 by METRO Staff

[IMAGE]MET2News-Metrolink2-2.jpg[/IMAGE]In December 2010, record-setting rains forced Southern California's Metrolink to scramble to maintain services for its customers when issues such as flooding and mudslides caused delays.

"There is sort of an adrenaline rush when trying to solve problems like these," said CEO John Fenton the morning after seven to eight inches of water flooded one of its tracks around 9:30 p.m. "I like to say that our staff is at our best when things are at their worst."

Fortunately, the storms only forced Metrolink to put its existing plans into action, explained Fenton, with the commuter rail system planning weeks ahead of Southern California's rainy season, which often becomes treacherous in many areas Metrolink serves.

"Success requires constant problem solving and lots of cooperation and teamwork," Fenton said. To prepare for the storms, the agency conducted a conference call at 11:00 p.m. the night before, with all the Los Angeles County CEOs, to review the details of their strategy and plans on handling service interruptions. They had to anticipate all possible hurdles, one of the biggest being freeway shutdowns.

"A big part of being successful in an outage is anticipation," said Fenton. That evening would be the biggest challenge, with the worst of the storm on its way. Problem solving tactics included establishing bus bridges and cleaning and inspecting tracks. Officials received a call at 4:00 a.m., the morning of the first storm, Fenton recalled, to bring in crews from a remote location to take measures to prevent mudslides and washouts on the tracks.

The morning after one storm was just finishing passing through, with a larger storm predicted to hit that night, Fenton and his staff convened in the "War Room" to both monitor the current situation and to make plans for the issues that may arise later.

In a small conference room, approximately 10 transit officials constantly reviewed rail monitor screens and worked to troubleshoot obstacles caused by the severe rainstorms. They received notifications on the status of the more than 500 miles of railroad they operate through a "bucket line" simulator as well as field reports and accounts from conductors, which appeared on multiple monitors placed throughout the room.

Some of the measures the commuter rail system has in place include round-the-clock surveillance of the situation with changes made to services on the fly, constant updates to its customers via its communications department, having equipment and crew on hand to work on damaged or flooded rails, and motorcoach and transit bus service when its trains are unable to run.

As of September 2010, Metrolink runs seven routes over 388 miles — 512 miles when including services shared with Amtrak — with 55 stations and 144 trains in operation, on average, during the weekdays, serving an area that spans Southern California from the mountains to the deserts to the beaches. Between April and June 2010, Metrolink served a total of 38,684 passengers.

The commuter rail system plans on having 137 new, state-of-the-art cab and passenger Hyundai-Rotem collision-absorption technology railcars, dubbed the Guardian fleet, in service by 2012 and is aggressively pursuing installation of positive train control by the 2015 federal mandate.

Additionally, the agency has partnered with "Wild at Work," an online business-to-business resource that reaches employees at more than 2,000 workplaces in the Metrolink service area. Employees of "Wild at Work" member companies receive coupons and special offers provided by 27,000 partner companies. Metrolink will be able to create special offers for this commuter population and promote its corporate pass program.

Other initiatives include enhancing customer service; station cleanliness; and introducing quiet cars.

 

View comments or post a comment on this story. (0 Comments)

More News

Metra to install suicide prevention signs

The signs will be developed and finalized as part of a Mental Health Awareness Symposium to be hosted by Metra in September to coincide with National Suicide Awareness Month.

Accident, no shows plague commute for LIRR, NJ Transit passengers

Some NJ TRANSIT trains have been canceled this week because engineers are choosing not to work under the terms of their contract amid the summer-long repair work at Penn Station.

Mayor says Miami-Dade can't afford to build more rail lines

Mayor Carlos Gimenez’s $534 million proposal for rapid-bus routes would indefinitely defer the Metrorail expansion promised voters in 2002 during a referendum for a half-percent transportation tax.

FTA, Maryland Transit Administration appeal judge's Purple Line decision

Ruling called for an additional environmental study of the light rail line, despite the fact the project had already been studied and signed-off on by the feds. 

Breakdowns, staffing part of growing Miami Metrorail safety concerns

When state inspectors visited Miami-Dade in late 2016, they concluded the county needed 84 working Metrorail cars a day but that mechanical problems left only 72 that could be deployed for service. State inspectors returned in late June and found Miami-Dade’s daily goal was to have only 60 Metrorail cars in service.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close