Calif.'s Metrolink weathers record storms, plans service upgrades

Posted on February 9, 2011 by METRO Staff

[IMAGE]MET2News-Metrolink2-2.jpg[/IMAGE]In December 2010, record-setting rains forced Southern California's Metrolink to scramble to maintain services for its customers when issues such as flooding and mudslides caused delays.

"There is sort of an adrenaline rush when trying to solve problems like these," said CEO John Fenton the morning after seven to eight inches of water flooded one of its tracks around 9:30 p.m. "I like to say that our staff is at our best when things are at their worst."

Fortunately, the storms only forced Metrolink to put its existing plans into action, explained Fenton, with the commuter rail system planning weeks ahead of Southern California's rainy season, which often becomes treacherous in many areas Metrolink serves.

"Success requires constant problem solving and lots of cooperation and teamwork," Fenton said. To prepare for the storms, the agency conducted a conference call at 11:00 p.m. the night before, with all the Los Angeles County CEOs, to review the details of their strategy and plans on handling service interruptions. They had to anticipate all possible hurdles, one of the biggest being freeway shutdowns.

"A big part of being successful in an outage is anticipation," said Fenton. That evening would be the biggest challenge, with the worst of the storm on its way. Problem solving tactics included establishing bus bridges and cleaning and inspecting tracks. Officials received a call at 4:00 a.m., the morning of the first storm, Fenton recalled, to bring in crews from a remote location to take measures to prevent mudslides and washouts on the tracks.

The morning after one storm was just finishing passing through, with a larger storm predicted to hit that night, Fenton and his staff convened in the "War Room" to both monitor the current situation and to make plans for the issues that may arise later.

In a small conference room, approximately 10 transit officials constantly reviewed rail monitor screens and worked to troubleshoot obstacles caused by the severe rainstorms. They received notifications on the status of the more than 500 miles of railroad they operate through a "bucket line" simulator as well as field reports and accounts from conductors, which appeared on multiple monitors placed throughout the room.

Some of the measures the commuter rail system has in place include round-the-clock surveillance of the situation with changes made to services on the fly, constant updates to its customers via its communications department, having equipment and crew on hand to work on damaged or flooded rails, and motorcoach and transit bus service when its trains are unable to run.

As of September 2010, Metrolink runs seven routes over 388 miles — 512 miles when including services shared with Amtrak — with 55 stations and 144 trains in operation, on average, during the weekdays, serving an area that spans Southern California from the mountains to the deserts to the beaches. Between April and June 2010, Metrolink served a total of 38,684 passengers.

The commuter rail system plans on having 137 new, state-of-the-art cab and passenger Hyundai-Rotem collision-absorption technology railcars, dubbed the Guardian fleet, in service by 2012 and is aggressively pursuing installation of positive train control by the 2015 federal mandate.

Additionally, the agency has partnered with "Wild at Work," an online business-to-business resource that reaches employees at more than 2,000 workplaces in the Metrolink service area. Employees of "Wild at Work" member companies receive coupons and special offers provided by 27,000 partner companies. Metrolink will be able to create special offers for this commuter population and promote its corporate pass program.

Other initiatives include enhancing customer service; station cleanliness; and introducing quiet cars.


View comments or post a comment on this story. (0 Comments)

More News

Bombardier contracted to extend Phoenix airport people mover

The contract is valued at approximately $305 million and includes options for three additional vehicles as well as for various vehicle retrofits and upgrades.  

Siemens, partners deliver automated peoplemover for Frankfurt Airport

The company will deliver 12 fully automated two-car trains equipped with GoA4 Communication Based Train Control Trainguard MT CBTC, the track work equipment, the station platform doors, communication system, depot equipment, and the power supply system.

FRA taking proactive approach to help railroads meet PTC requirement

At the direction of Secretary Elaine L. Chao, the FRA is taking a proactive approach to ensure railroads acquire, install, test, and fully implement certified PTC systems in time to meet the congressional interim deadline of Dec. 31, 2018.

Despite federal uncertainty, N.C. light rail project optimistic about funding

Half of the Durham-Orange light rail’s cost — totaling over a billion dollars — is expected to come from the federal government.

Las Vegas Monorail unveils Google Pay mobile ticketing

The Monorail now offers riders the ability to quickly and easily purchase fares online and use their phone at the fare gates for immediate transit access to everything along the Las Vegas Strip.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment



Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close