Mo., Amtrak to make track improvements

Posted on April 28, 2009

On Monday, representatives of the State of Missouri; the city of California, Mo.; Union Pacific Railroad and Amtrak kicked off the construction of a new $8.1 million, 9,000-foot railroad side track to add capacity and reduce delays on the route used by Amtrak Missouri River Runner trains between Kansas City and St. Louis.  

The new siding, located just west of California, will unclog a major “bottleneck” caused by a 25-mile stretch of single track and enable slower freight trains to move off the main line, enabling faster Amtrak trains to pass and reduce delays by nearly 17 percent, annually.

When finished in December 2009, the siding will accommodate the mile-and-a-half long Union Pacific coal trains that haul low-sulfur coal from Wyoming to electric utilities in the St. Louis area and eastern power generation facilities. The Missouri Department of Transportation (MoDOT) secured the funding for this project from state funds, complemented with a federal grant from the Federal Railroad Administration.

This location was chosen after a University of Missouri study estimated a siding in this area would annually reduce delays to Amtrak trains by nearly 17 percent. MoDOT commissioned the study in 2006 in order to determine where rail line capacity enhancements should be made to improve train velocity.

View comments or post a comment on this story. (0 Comments)

More News

Ill. bill doubles fines for drivers who illegally cross railroad tracks

The legislation doubles the fines from $250 to $500 for a first offense and from $500 to $1,000 for a second or subsequent offense.

FTA's Flowers testifies on D.C. Metro rail safety oversight progress

Through a comprehensive Safety Management Inspection, three Safety Directives, two immediate action letters, and ongoing inspection and investigation activity FTA safety oversight is requiring WMATA to take numerous positive actions to improve safety for passengers and workers.

Siemens consortium to deliver 22 trains to Bangkok

Delivery of the first metro trains is scheduled in 2018, and the order will be completed in the following year.

Sacramento RT considering closing light rail line indefinitely

The agency opened its $44 million Green Line only four years ago; however, the line currently averages only 440 boardings a day with limited service, and costs RT $330,000 annually to operate.

L.A. Metro celebrates launch of Expo Line to Santa Monica

The 6.6-mile Expo extension runs from Culver City to Santa Monica and includes seven stations. Ridership on the new portion is projected to total 18,000 to 20,000 weekday boardings after the first year of service. The travel time from downtown L.A. to the Downtown Santa Monica Station is 48 minutes.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close