N.J. Gov.: ARC tunnel project canceled

Posted on October 8, 2010

[IMAGE]NJ-Transit-ARC-tunnel-cavern-rendering-full-2.jpg[/IMAGE]On Thursday, New Jersey Gov. Chris Christie accepted the recommendation of the ARC Project Executive Committee to terminate the ARC Project based on a 30-day review which confirmed the project is expected to substantially exceed its current budget. Based on calculations by the Federal Transit Administration (FTA) and New Jersey Transit (NJ Transit), the final budget is expected to top $11 billion and could exceed as much as $14 billion, compared to the project’s current budget of $8.7 billion.

 

The federal commitment is capped at $3 billion and the federal government requires that any costs above $8.7 billion must be absorbed by the State of New Jersey. Cost overruns are estimated to be in a range from more than $2 billion to over $5 billion.

 

Jim Weinstein, Executive Director of NJ Transit stated, “While we recognize the importance and value of a cross-Hudson transportation improvement project, the current economic climate in New Jersey simply does not allow for this project to continue considering the substantial additional costs that are required. The ARC project is just not a financially viable project that we can responsibly move forward.”

 

Gov. Christie stated, “I have made a pledge to the people of New Jersey that on my watch I will not allow taxpayers to fund projects that run over budget with no clear way of how these costs will be paid for. Considering the unprecedented fiscal and economic climate our State is facing, it is completely unthinkable to borrow more money and leave taxpayers responsible for billions in cost overruns. The ARC project costs far more than New Jersey taxpayers can afford and the only prudent move is to end this project.

 

“There is no doubt that transportation projects are critical to creating jobs and growing our economy. I have asked Commissioner Simpson and Executive Director Weinstein to work with all interested parties — Amtrak, the Federal Transit Administration, the Port Authority, the State and City of New York and our Congressional delegation — to explore approaches to modernize and expand capacity for the Northeast Corridor. However, any future project must recognize the regional and national scale of such an effort and work within the scope of the State’s current fiscal and economic realities,” Gov. Christie concluded.

 

On September 10, 2010, the ARC Project Executive Committee recommended and the Governor directed a 30-day pause in the execution of new contracts and any new expenditures in order to fully understand the status of project funding and the likely cost of moving the project forward as originally planned. Based on this detailed financial analysis, the ARC project will be terminated and staff will immediately begin an expeditious and orderly shutdown of the project.

 

EXTRA: To read about the project in a June 2009 METRO interview with ex-NJ TRANSIT Executive Director Richard Sarles, click here.

 

To visit the ARC Tunnel project website, click here.

View comments or post a comment on this story. (0 Comments)

More News

Ill. bill doubles fines for drivers who illegally cross railroad tracks

The legislation doubles the fines from $250 to $500 for a first offense and from $500 to $1,000 for a second or subsequent offense.

FTA's Flowers testifies on D.C. Metro rail safety oversight progress

Through a comprehensive Safety Management Inspection, three Safety Directives, two immediate action letters, and ongoing inspection and investigation activity FTA safety oversight is requiring WMATA to take numerous positive actions to improve safety for passengers and workers.

Siemens consortium to deliver 22 trains to Bangkok

Delivery of the first metro trains is scheduled in 2018, and the order will be completed in the following year.

Sacramento RT considering closing light rail line indefinitely

The agency opened its $44 million Green Line only four years ago; however, the line currently averages only 440 boardings a day with limited service, and costs RT $330,000 annually to operate.

L.A. Metro celebrates launch of Expo Line to Santa Monica

The 6.6-mile Expo extension runs from Culver City to Santa Monica and includes seven stations. Ridership on the new portion is projected to total 18,000 to 20,000 weekday boardings after the first year of service. The travel time from downtown L.A. to the Downtown Santa Monica Station is 48 minutes.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close