Phoenix Metro taps design-build method for rail extension

Posted on July 27, 2011

Phoenix-based Metro light rail will take advantage of the competitive market and gain the early insight of a contractor with a design-build delivery method for its 3.1-mile Central Mesa extension, the agency announced.

The decision is a departure from Metro's typical project delivery approach of design-bid-build, but it works in favor of building a quality product in this economy and in such a way that is supportive of the local business community.

"The challenging economy presents us with an opportunity to think creatively about how we move projects forward," said Metro CEO Steve Banta. "A quality design/builder can help us navigate towards a successful project that will best serve the neighboring community and the public dollar. It will also benefit the project's timeline."

A strong benefit of the design-build approach is that the construction contractor will come on board early to work directly with the designer to build plans that are workable for both parties. Contractor expertise will also help to build a construction schedule that meets the needs of the agency, project and community.

The Central Mesa project team is now finalizing preliminary engineering. These plans will be delivered to a design/build team for further development in spring 2012. A Request for Qualifications, to initiate the design-build procurement, has been issued as of Sunday, July 24.

Future project milestones remain intact. Utility relocation will begin in spring 2012 with the project to be complete in 2016.

View comments or post a comment on this story. (0 Comments)

More News

Former Santa Clara VTA chief hired to oversee Honolulu rail project

Michael Burns will be responsible for overseeing the rail project’s finances, as well as the functioning of the Honolulu Authority for Rapid Transportation board.

Alstom to extend Algeria's Constantine Tramway

Alstom, which will extend the tramway by 6 miles, will supply the integrated system, tracks, catenaries, telecommunications and signalling, substations and ticketing equipment.

$8.2B invested along 20 miles of Valley Metro light rail

Economic development within one-half mile of the system has been stimulated by ridership that has exceeded original projections. Valley Metro began compiling development activity since construction started in 2005 as part of an economic development database.

Alstom to deliver 17 trains to Algeria

The Coradia Polyvalent for Algeria is a dual-mode train (diesel and electric, 25 kV) able to travel at speeds up to 99 mph. The train has six carriages and provides capacity for 265 passengers.

Fla.'s TriRail adds bike car

The new bike car contains 14 racks that will provide more room to maneuver bicycles on and off the train. A set of seats were removed from the lower level of the vehicle to make room for the bike racks.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The resource for managers of class 1-7 truck Fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close