Phoenix Metro taps design-build method for rail extension

Posted on July 27, 2011

Phoenix-based Metro light rail will take advantage of the competitive market and gain the early insight of a contractor with a design-build delivery method for its 3.1-mile Central Mesa extension, the agency announced.

The decision is a departure from Metro's typical project delivery approach of design-bid-build, but it works in favor of building a quality product in this economy and in such a way that is supportive of the local business community.

"The challenging economy presents us with an opportunity to think creatively about how we move projects forward," said Metro CEO Steve Banta. "A quality design/builder can help us navigate towards a successful project that will best serve the neighboring community and the public dollar. It will also benefit the project's timeline."

A strong benefit of the design-build approach is that the construction contractor will come on board early to work directly with the designer to build plans that are workable for both parties. Contractor expertise will also help to build a construction schedule that meets the needs of the agency, project and community.

The Central Mesa project team is now finalizing preliminary engineering. These plans will be delivered to a design/build team for further development in spring 2012. A Request for Qualifications, to initiate the design-build procurement, has been issued as of Sunday, July 24.

Future project milestones remain intact. Utility relocation will begin in spring 2012 with the project to be complete in 2016.

View comments or post a comment on this story. (0 Comments)

More News

Ill. bill doubles fines for drivers who illegally cross railroad tracks

The legislation doubles the fines from $250 to $500 for a first offense and from $500 to $1,000 for a second or subsequent offense.

FTA's Flowers testifies on D.C. Metro rail safety oversight progress

Through a comprehensive Safety Management Inspection, three Safety Directives, two immediate action letters, and ongoing inspection and investigation activity FTA safety oversight is requiring WMATA to take numerous positive actions to improve safety for passengers and workers.

Siemens consortium to deliver 22 trains to Bangkok

Delivery of the first metro trains is scheduled in 2018, and the order will be completed in the following year.

Sacramento RT considering closing light rail line indefinitely

The agency opened its $44 million Green Line only four years ago; however, the line currently averages only 440 boardings a day with limited service, and costs RT $330,000 annually to operate.

L.A. Metro celebrates launch of Expo Line to Santa Monica

The 6.6-mile Expo extension runs from Culver City to Santa Monica and includes seven stations. Ridership on the new portion is projected to total 18,000 to 20,000 weekday boardings after the first year of service. The travel time from downtown L.A. to the Downtown Santa Monica Station is 48 minutes.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close