MTA's Metro-North assessing flood damage of line

Posted on September 9, 2011

A team of engineers hired by the Metropolitan Transportation Authority's (MTA) Metro-North Railroad is inspecting and assessing the catastrophic flood damage to the Port Jervis Line. Meanwhile buses are providing alternative service for the 2,300 people who normally use the line each weekday.

Significant damage to the line identified last week following Hurricane Irene by an aerial inspection includes up to 40 washout locations, including three washouts each at least a thousand feet long near Sloatsburg, a 400-foot section of track washed out just south of Sloatsburg, significant damage to several railroad bridges and exposure of what had been a subterranean signal cable.

Following through on MTA Chairman Jay Walder's emergency powers invoked to expedite rebuilding the devastated line, work began last week on an on-the-ground assessment of damage from the storm and a final condition assessment report is expected by the end of the month.

AECOM began a conditions analysis of track and structures along 14 of the hardest hit miles of the right-of-way as well as a hydrology study of the area. Their sub-consultant, Systra, is assessing all railroad communications and signal systems, while M.G. McLaren will assess damage to the rail bridges in the affected area.

AECOM was issued a Notice to Proceed for emergency work, not-to exceed $500,000.

Metro-North is studying its options to improve service.


View comments or post a comment on this story. (0 Comments)

More News

Charlotte Area Transit launches LYNX Blue Line extension

The 9.3-mile extension, coined the Blue Line Extension (BLE) during construction, continues the alignment north from the previous terminus stop at 7th Street Station and now culminates at UNC Charlotte’s main campus.

Protran Technology names new director of sales

Kyley Holmstrom brings over 20 years of experience in senior management and sales, engineering operations, and purchasing in the rail industry, to the position.

NJ Transit continues closing gap on overcrowded trains

The agency's team was in Maryland earlier this week to inspect 20 railcars as a lease was being worked out.

Bombardier secures contract extension to maintain London Overground trains

The contract, originally signed in 2006 will now continue until 2030, removing a previous contract break in 2023.

San Diego NCTD celebrates SPRINTER's 10th Anniversary

The North County Transit District will hold community outreach and educational events through various SPRINTER stations.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment



Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close