N.Y.'s Grand Central to be more energy efficient with upgrades

Posted on April 24, 2012

The largest energy efficiency project that the New York Metropolitan Transportation Authority (MTA) has ever undertaken with the New York Power Authority (NYPA) is under way in Grand Central Terminal, which will reduce annual carbon emissions by 10,000 tons.

Behind-the-scenes equipment that keeps Grand Central cool in the summer, warm in the winter and flushed with fresh air all year round is being upgraded though a $22 million partnership between NYPA and MTA Metro-North Railroad. The energy efficiency project will conserve energy and save an estimated $3 million a year.

Deep below the gleaming marble concourse and high above the constellation ceiling is a myriad of pumps, chillers, fans, compressors, cooling towers, meters and miles of high-pressure steam pipes, many of them a century old. Many of these systems are being replaced throughout the 48-acre terminal that extends seven stories above ground and 150 feet below sea level.

The upfront costs of the new, energy-efficient equipment will be borne by NYPA and be repaid annually over about 11 years by Metro-North with the money it saves as the result of a reduction in energy use. Installation began this month and will be completed by the end of 2013.

Over the past year, Metro-North undertook $1.5 million in energy efficiency improvements in Grand Central including 11 new escalator controllers that save 25-40% in electricity, 2,600 new lighting fixtures, 59 new motors of 5 horsepower or greater and a new sewage ejector. Meters also were installed on the steam, chilled water, compressed air and gateway electric feeders to collect data for the metering and verification portion of the project.

View comments or post a comment on this story. (0 Comments)

More News

FRA makes $25M available for rail infrastructure safety upgrades

Applicants can request funds for safety improvements to railroad infrastructure, including railroad crossings, track, tunnels, bridges, yards and other areas.

NJ TRANSIT's Hudson-Bergen line running modified service for 3rd day

Service has been hampered since overhead catenary wires were yanked down when a dump truck lowered its bed two days ago. There is no timetable for the repair of the wires.

D.C. Metro rules out power cables as factor in recent smoke incident

Passengers aboard the train described a tense atmosphere, with smoke in some of the railcars, flames visible outside the train and the odor of electrical smoke evoking memories of the Jan. 12, 2015, L’Enfant Plaza Metro station incidnet that left one rider dead and scores sickened

Alstom awarded major re-signaling project in the UK

Collaborated with Network Rail to develop an interlocking solution based on Alstom’s Smartlock range that will be ready for ETCS installation allowing trains with ETCS capability to operate on that section of the line.

Sacramento RT taps HDR Inc. for streetcar design

The contract outlines a $10 million budget to construct the streetcar line.The city wants the money to come from property owners near the streetcar line, but they rejected it in a vote last year.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close