Rail

Measures enable S.F. subway project to move forward

Posted on May 2, 2012

The San Francisco Municipal Transportation Agency (SFMTA), which oversees the transportation network in the city, announced the San Francisco board of supervisors and the SFMTA board of directors unanimously approved several resolutions that will move the Central Subway Project forward.

Of the five measures approved by the board of supervisors, one supports an assurance funding plan that will allow the Central Subway to advance if state bond funds earmarked for the project are delayed. The SFMTA board of directors approved a similar measure. The board of supervisors also passed four resolutions approving the acquisition of temporary construction licenses, allowing work related to the Central Subway tunnel to commence around Union Square.

The resolutions supporting an assurance funding plan allow the SFMTA to issue revenue bonds in the event of a shortfall or delay in state Proposition 1A High Speed Rail Connectivity funds. The Federal Transit Administration, which is expected to provide nearly $1 billion in funding to the Central Subway Project through its New Starts program, requested this additional assurance as a backup plan.

The other resolutions passed by the board of supervisors approve the acquisition of four temporary construction licenses around Union Square. Work to prepare the project alignment for tunneling is on track to begin in June in this area. The temporary construction licenses would authorize the SFMTA to acquire the rights via eminent domain to install temporary piles that cross into privately owned property dozens of feet below ground. The SFMTA continues to negotiate a license agreement with the owners of the four properties.

The assurance funding measure and the four construction license resolutions were unanimously approved by San Francisco’s 11 supervisors. The SFMTA has the authority under the city’s charter to issue revenue bonds to support capital projects.

The Central Subway is expected to open to the public in 2019.

View comments or post a comment on this story. (0 Comments)

More News

Alstom opens new Brazilian Citadis production line

The new production facility will serve the Brazilian market and, in a near future, the Latin America region where a number of new tramway projects are emerging. When fully operational, the facility will employ around 150 people.

FRA ramps up campaign to address nationwide grade crossing safety

The first phase of the effort calls upon local law enforcement agencies to show a greater presence at grade crossings, issue citations to drivers that violate rules of the road at crossings and consider rapid implementation of best practices for grade crossing safety.

S.C. city seeking elevated transit line bids

The first phase of the plan would construct a four-mile section elevated guideway above a section of abandoned railroad tracks. The first section of the elevated railway could connect Clemson University's International Center for Automotive Research campus with downtown Greenville.

MBTA considers options to compensate riders for snow woes

One option included offering one week of free fares throughout the system ($6 million in lost revenue).

Calif.'s Metrolink puts PTC into revenue service demo mode

With this latest accomplishment, Metrolink remains on track to become the nation’s first passenger rail system to have a fully implemented, interoperable PTC system in place.

See More News

Post a Comment

Post Comment

Comments (0)

Please sign in or register to .    Close