Sound Transit completes $1.9B Seattle rail tunnel link

Posted on May 16, 2012

Sound Transit contractors have connected the University Link light rail tunnels with the Downtown Seattle Transit Tunnel (DSTT). The tunnel boring machine, nicknamed "Brenda," recently completed its one-mile trip on the second tunnel between Capitol Hill and downtown.

The tunnel-boring machine removal of a headwall between the mining operations and the DSTT means there are now twin tunnels running 3.1 miles between downtown Seattle and the University of Washington. The contractor team, JCM U-Link Joint Venture, mined two tunnels about a mile long between the site of the future Capitol Hill Station and downtown Seattle. A separate contractor completed the twin tunnels between UW and Capitol Hill in early April.

The contractors will now focus on completing 21 cross passages between the twin tunnels by early 2013.

Overall, the $1.9 billion project is about halfway complete and scheduled to open in 2016. Between now and then contractors have to finish stations at UW and Capitol Hill, install communications and power systems and test the new line.

The expansion with stations in the heart of Capitol Hill and the University of Washington will provide unparalleled speed and reliability through Seattle's most dense neighborhoods. A trip from Husky Stadium to Westlake will take six minutes and is expected to add 70,000 riders to the system by 2030.

The corridor includes three major universities/colleges — the University of Washington (UW), Seattle University and Seattle Central Community College (SCCC) — with a combined enrollment of more than 50,000 students.

More News

WSP USA projects recognized with three Calif. transportation awards

The Exposition Line Light Rail in Los Angeles received the California Transportation Foundation's Overall Project of the Year award.

City Council approves transfer of Atlanta Streetcar to MARTA

The $99 million streetcar opened in December 2014 amid sky-high expectations, but ridership failed to meet expectations in its first year and plummeted nearly 60% after the city began charging $1 to ride.

Honolulu officials submit new light rail plan to FTA

The total project cost included in the new plan remains at $8.165 billion for capital costs exclusive of finance charges, with full revenue service scheduled for December 2025.

Alstom to supply traction system in Chengdu, China

The contract is worth approximately $68.3 million. The line is expected to start revenue service by the end of 2019.

Hyperloop One announces 10 winners of 'Global Challenge'

The company will commit meaningful business and engineering resources and work closely with each of the winning teams/routes to determine their commercial viability.

See More News

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close