Sound Transit completes $1.9B Seattle rail tunnel link

Posted on May 16, 2012

Sound Transit contractors have connected the University Link light rail tunnels with the Downtown Seattle Transit Tunnel (DSTT). The tunnel boring machine, nicknamed "Brenda," recently completed its one-mile trip on the second tunnel between Capitol Hill and downtown.

The tunnel-boring machine removal of a headwall between the mining operations and the DSTT means there are now twin tunnels running 3.1 miles between downtown Seattle and the University of Washington. The contractor team, JCM U-Link Joint Venture, mined two tunnels about a mile long between the site of the future Capitol Hill Station and downtown Seattle. A separate contractor completed the twin tunnels between UW and Capitol Hill in early April.

The contractors will now focus on completing 21 cross passages between the twin tunnels by early 2013.

Overall, the $1.9 billion project is about halfway complete and scheduled to open in 2016. Between now and then contractors have to finish stations at UW and Capitol Hill, install communications and power systems and test the new line.

The expansion with stations in the heart of Capitol Hill and the University of Washington will provide unparalleled speed and reliability through Seattle's most dense neighborhoods. A trip from Husky Stadium to Westlake will take six minutes and is expected to add 70,000 riders to the system by 2030.

The corridor includes three major universities/colleges — the University of Washington (UW), Seattle University and Seattle Central Community College (SCCC) — with a combined enrollment of more than 50,000 students.

View comments or post a comment on this story. (0 Comments)

More News

Hyperloop to build full-scale track next year

The Quay Valley, Calif. Hyperloop track will be built using HTT’s tube, capsule and station models. It will be instrumental in optimizing passenger system needs — such as loading, departure and safety considerations — to ensure Hyperloop is ready for larger-scale operation.

Keolis/MBTA make strides with commuter rail snowstorm recovery

Milestones include the completion of snow and ice removal from all platforms and critical rail switches system-wide, as well as the addition of supplemental trains, doubledecker and standard passenger cars to increase capacity and combat overcrowding.

Alstom to deliver to Sydney Citadis X05

Company is responsible for the integrated tramway system, which includes the design, delivery and commissioning of 30 coupled Citadis X05 trams; power supply equipment, including APS -ground power supply; signaling systems, the energy recovery system HESOP, depot equipment and maintenance.

Ann Arbor transit official urged MDOT not to lease railcars

In 2009, more than a year before MDOT signed a contract to lease and refurbish the double-decker railcars, which since have cost the state about $12 million, an Ann Arbor transit official told MDOT the cars were not suitable for proposed commuter rail services because they didn't meet federal requirements.

Hitachi purchases manufacturer of Honolulu's rail system

Finmeccanica owns all of AnsaldoBreda, which is unprofitable, and 40% of Ansaldo STS, which is profitable, according to the report. The two Ansaldo companies formed a joint venture, Ansaldo Honolulu JV, to design and build the 20-mile, 21-station elevated train system for Oahu under a $1.4 billion contract.

See More News

Post a Comment

Post Comment

Comments (0)

Please sign in or register to .    Close