Houston Metro targets worker safety during high temps

Posted on August 15, 2012

Houston's MetroRail and contractor Houston Rapid Transit (HRT) are blazing light-rail tracks on the North, East and Southeast lines, and chilling 9,000 pounds of ice each day to make sure crews stay cool enough to work during the season’s high temperatures.

Maintaining safety on the new lines (scheduled to open in 2014) calls for expertise and coordination and Safety Coordinator Daniel “Red” Motley has plenty to offer. Motley comes to Metro with 30-plus years of experience, most recently in the mid-east as construction safety leader for one of the largest petro-chemical projects ever attempted. Today, he is in the field daily, checking on rail expansion crews and work conditions.

Crews are given regular training to prevent and recognize heat illness. Construction schedules are adapted for worker safety so activities start between 5 a.m. and 6 a.m. and usually end by 2 p.m. Crews are instructed to be aware of and limit disturbance to the community during early hours.

“Safety is a core value for both Metro and HRT,” notes Douglas Reehl, HRT project director. “We firmly believe that every accident is preventable. A safe workplace is our goal, and we strive constantly to find new strategies to meet it.”

The heat index is tracked daily, Reehl says, and precautions taken, but work halts when the index reaches 105. In addition to earlier work hours, each crew has extended break time and shaded pop-up tents and tables, with water coolers, sports drinks and access to ice. HRT trucks also make daily deliveries of fresh oranges and popsicles to crews to maintain hydration.

More News

FRA makes $25M available for rail infrastructure safety upgrades

Applicants can request funds for safety improvements to railroad infrastructure, including railroad crossings, track, tunnels, bridges, yards and other areas.

NJ TRANSIT's Hudson-Bergen line running modified service for 3rd day

Service has been hampered since overhead catenary wires were yanked down when a dump truck lowered its bed two days ago. There is no timetable for the repair of the wires.

D.C. Metro rules out power cables as factor in recent smoke incident

Passengers aboard the train described a tense atmosphere, with smoke in some of the railcars, flames visible outside the train and the odor of electrical smoke evoking memories of the Jan. 12, 2015, L’Enfant Plaza Metro station incidnet that left one rider dead and scores sickened

Alstom awarded major re-signaling project in the UK

Collaborated with Network Rail to develop an interlocking solution based on Alstom’s Smartlock range that will be ready for ETCS installation allowing trains with ETCS capability to operate on that section of the line.

Sacramento RT taps HDR Inc. for streetcar design

The contract outlines a $10 million budget to construct the streetcar line.The city wants the money to come from property owners near the streetcar line, but they rejected it in a vote last year.

See More News

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close