All but one of NJ Transit rail lines fully restored

Posted on November 21, 2012

All but one NJ Transit rail line is running full or modified service. This includes the restoration of service along the North Jersey Coast Line, which suffered the brunt of the damage wrought by Hurricane Sandy.

Additionally, with the completion of repairs to a key Amtrak-owned electrical substation in Kearny that will generate additional power to the Northeast Corridor, NJ Transit will be operating approximately 90% of its normal peak period service into New York Penn Station. Main, Bergen County, Pascack Valley and Port Jervis Line trains will resume stopping at Secaucus Junction as a result of the additional rail capacity opened along the Northeast Corridor.

“This is a major milestone in our continuing, post-Sandy recovery.  The devastation wrought on the North Jersey Coast Line was the worst sustained throughout our system,” said Transportation Commissioner and NJ Transit Board Chairman James Simpson. “While we are not out of the woods and the recovery process continues, the restoration of this critical rail service is a major step forward for the Garden State.”

The restoration of service on the North Jersey Coast Line completes the full or partial restoration of all NJ Transit rail lines. More than 30 miles of North Jersey Coast Line track sustained severe damage during the storm, including extensive rail washouts (no ballast under the tracks) between South Amboy and Bay Head. The River Drawbridge over Raritan Bay was severely damaged following a collision between two tugboats in addition to a record storm surge. The Morgan Drawbridge in South Amboy also sustained severe damage following a record storm surge and the impact from recreational boats and a cargo container.

“The restoration of NJ Transit’s rail lines within 18 days of Sandy is a tremendous credit to the commitment, professionalism and the dedication of our employees,” said NJ Transit Executive Director James Weinstein. “In this time of Thanksgiving, I would like to specifically offer our thanks to our employees for their service, as well as to customers for their patience and understanding during this difficult time.”

View comments or post a comment on this story. (0 Comments)

More News

Feds wants more proof of local money for Durham-Orange light rail line

Go Triangle expects its Board of Trustees to vote April 26 on a $70 million engineering contract, which would be executed only after the FTA allows the project to advance.

SEPTA trains collide, injuring 4

Crews are still working to remove the 18 cars involved, with each car weighing about 37 tons. The NTSB is on the scene and fully in charge of the investigation.

Minn. legislators attempting to move $900M from rail to roads, bridges

GOP legislators have long sought to block planning and funding for light-rail projects, saying they put metro-area priorities above rural Minnesota.

Alstom secures $105M Australian trainset contract

The contract will expand PTV’s fleet to 101 trains (606 cars) delivered from Alstom’s manufacturing facility in Ballarat since 2002.

DC Streetcar fares to remain free

The decision to hold off on charging fares was based on two reasons — District Department of Transportation feared charging even $1 per ride would scare away passengers and charging a fare would actually cost the District money.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close