Calif. VTA may extend light rail

Posted on November 21, 2012

The Santa Clara Valley Transportation Authority (VTA) is proposing to extend the existing Mountain View to Winchester light rail line by 1.6 miles by way of the Vasona Light Rail Extension Project. The extension would begin at the existing Winchester Station in Campbell and continue within the VTA right-of-way to the Town of Los Gatos.

VTA has prepared a Supplemental Draft Environmental Impact Report/Environmental Assessment (SEIR/EA) for public review. In accordance with current state and federal environmental laws and guidelines, the Draft SEIR/EA presents design changes to the project that were previously approved in 2000 while also disclosing the environmental impacts of those design changes.

The original Vasona Corridor Project proposed light rail service from downtown San Jose through the City of Campbell to the Town of Los Gatos. The first portion, downtown San Jose to the Winchester Station in Campbell, opened for revenue service on Oct. 1, 2005, adding 5.3 miles and eight stations to VTA’s 36.9-mile light rail system.  

“As the fourth major light rail extension since 1999, the line to Campbell has provided a convenient and economical travel option for West Valley residents, given VTA customers direct access to the multi-modal San Jose Diridon transit hub, and doubled light rail service along North First Street in San Jose,” said Joe Pirzynski, Town of Los Gatos council member and VTA board vice chair.

The proposed extension will be implemented in two phases based on funding availability. Project features in Phase 1 include construction of a double set of light rail tracks at the Winchester Station; expansion of parking capacity at the Winchester Station; and a new Vasona Junction Station along with a park and ride lot.

Phase 2 would construct a new Hacienda Light Rail Station with an optional park and ride lot. The cost of the project is estimated to be $175 million.

View comments or post a comment on this story. (0 Comments)

More News

Feds cancel $929 million in grant funds for California's high-speed rail

U.S. DOT is also actively exploring legal options to seek the return of $2.5 billion in federal funds.

Metra to buy 15 remanufactured locomotives

Supplier, Progress Rail will take existing EMD SD70MAC freight locomotives and upgrade and configure them for passenger use.

Meet three engineers rebuilding the BART system

Profiling projects they work on and ask about their successes and challenges along the way.

FRA issues national trespass prevention strategy

4,242 pedestrians were killed or injured while trespassing on railroad property nationwide during a four-year period.

Keolis adds light rail to its Australian multimodal network

The approximate 1.7-mile long network features six stations and runs between Wickham and Pacific Park.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation