Calif.’s VTA marks BART station construction milestone

Posted on April 4, 2013

The Santa Clara Valley Transportation Authority (VTA) will celebrate one-year construction milestones for the Bay Area Rapid Transit District (BART) Silicon Valley Berryessa Extension Project on April 5.

Over the past 12 months, construction accomplishments on the Berryessa Extension Project include demolition and site preparation at station areas in Milpitas and San Jose; realignment and restoration of the Upper Penitencia Creek at the future Berryessa Station; relocation of major utilities all along the 10-mile project corridor and in the station areas; the commencement of station roadway and bridge construction; early support work for the elevated track structure at the Berryessa Station site; completion of the BART bridge over Kato Road; and all but finishing touches on the Kato Road grade separation.

The Kato Road Grade Separation Project is the first of eleven grade separations needed to complete the 10-mile BART extension into Santa Clara County. Separating the BART system from automobiles, pedestrians and freight enhances safety and contributes to the efficiency of BART service.  

The remaining finishing work on the Kato Road Grade Separation Project includes the installation of safety railings, landscape and irrigation, and removal of traffic mitigation measures in nearby intersections. Final project completion is set for early summer 2013.
 
During the five-year period that represents the height of project construction, jobs related to the 10-mile BART Silicon Valley Berryessa Extension Project translate to an average of 3,300 annual full-time jobs per year. In addition to job creation, the return on investment for every dollar spent on the project is $4 to $10.

View comments or post a comment on this story. (0 Comments)

More News

FRA makes $25M available for rail infrastructure safety upgrades

Applicants can request funds for safety improvements to railroad infrastructure, including railroad crossings, track, tunnels, bridges, yards and other areas.

NJ TRANSIT's Hudson-Bergen line running modified service for 3rd day

Service has been hampered since overhead catenary wires were yanked down when a dump truck lowered its bed two days ago. There is no timetable for the repair of the wires.

D.C. Metro rules out power cables as factor in recent smoke incident

Passengers aboard the train described a tense atmosphere, with smoke in some of the railcars, flames visible outside the train and the odor of electrical smoke evoking memories of the Jan. 12, 2015, L’Enfant Plaza Metro station incidnet that left one rider dead and scores sickened

Alstom awarded major re-signaling project in the UK

Collaborated with Network Rail to develop an interlocking solution based on Alstom’s Smartlock range that will be ready for ETCS installation allowing trains with ETCS capability to operate on that section of the line.

Sacramento RT taps HDR Inc. for streetcar design

The contract outlines a $10 million budget to construct the streetcar line.The city wants the money to come from property owners near the streetcar line, but they rejected it in a vote last year.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close