Calif.’s VTA marks BART station construction milestone

Posted on April 4, 2013

The Santa Clara Valley Transportation Authority (VTA) will celebrate one-year construction milestones for the Bay Area Rapid Transit District (BART) Silicon Valley Berryessa Extension Project on April 5.

Over the past 12 months, construction accomplishments on the Berryessa Extension Project include demolition and site preparation at station areas in Milpitas and San Jose; realignment and restoration of the Upper Penitencia Creek at the future Berryessa Station; relocation of major utilities all along the 10-mile project corridor and in the station areas; the commencement of station roadway and bridge construction; early support work for the elevated track structure at the Berryessa Station site; completion of the BART bridge over Kato Road; and all but finishing touches on the Kato Road grade separation.

The Kato Road Grade Separation Project is the first of eleven grade separations needed to complete the 10-mile BART extension into Santa Clara County. Separating the BART system from automobiles, pedestrians and freight enhances safety and contributes to the efficiency of BART service.  

The remaining finishing work on the Kato Road Grade Separation Project includes the installation of safety railings, landscape and irrigation, and removal of traffic mitigation measures in nearby intersections. Final project completion is set for early summer 2013.
 
During the five-year period that represents the height of project construction, jobs related to the 10-mile BART Silicon Valley Berryessa Extension Project translate to an average of 3,300 annual full-time jobs per year. In addition to job creation, the return on investment for every dollar spent on the project is $4 to $10.

View comments or post a comment on this story. (0 Comments)

More News

Feds wants more proof of local money for Durham-Orange light rail line

Go Triangle expects its Board of Trustees to vote April 26 on a $70 million engineering contract, which would be executed only after the FTA allows the project to advance.

SEPTA trains collide, injuring 4

Crews are still working to remove the 18 cars involved, with each car weighing about 37 tons. The NTSB is on the scene and fully in charge of the investigation.

Minn. legislators attempting to move $900M from rail to roads, bridges

GOP legislators have long sought to block planning and funding for light-rail projects, saying they put metro-area priorities above rural Minnesota.

Alstom secures $105M Australian trainset contract

The contract will expand PTV’s fleet to 101 trains (606 cars) delivered from Alstom’s manufacturing facility in Ballarat since 2002.

DC Streetcar fares to remain free

The decision to hold off on charging fares was based on two reasons — District Department of Transportation feared charging even $1 per ride would scare away passengers and charging a fare would actually cost the District money.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close