MTA wraps Grand Central Terminal blasting

Posted on April 10, 2013

Sandhogs working on the New York Metropolitan Transportation Authority’s (MTA) East Side Access megaproject have concluded major blasting under Grand Central Terminal, where they are building two enormous caverns 160 feet below street level that will house eight tracks for Long Island Rail Road (LIRR) trains.

Since March 7, 2007, nearly 1,000 employees working 24 hours a day, five days a week, have completed more than 2,400 controlled blasts — all without affecting the nearby operations of MTA Metro-North Railroad or the New York City Subway.

Approximately 857,000 cubic yards of rocky muck were excavated and removed, enough to cover the entirety of Central Park one foot deep.

“This is a very significant milestone for the East Side Access project,” said Dr. Michael Horodniceanu, president, MTA capital construction. “The caverns are essentially now fully excavated. Much work remains to be done to build the platforms and tracks and finish what is currently raw, cave-like space. But we now have a fully built shell in which all future work will take place.”

Each blast was overseen by an FDNY-licensed blaster. To conduct a blast, teams of sandhogs drill hundreds of holes measuring 1½ inches in diameter into the mica-inflected granite schist that forms the bedrock of Midtown Manhattan. Together, the holes are loaded with 200 pounds to 500 pounds of an explosive powder known as Emulex. After the sandhogs clear into a safe area, the Blaster-in-Charge issues a warning — “fire in the hole!” — and triggers the blast.

The contractors, a joint venture of Dragados USA Inc., and Judlau Contracting Inc., are continuing to perform miscellaneous concrete work until their contract is complete in June. They expect that they may need to make additional small blasts that will trim out pieces of rock in the cavern.

In addition to the blasting, the caverns under Grand Central have been excavated in part by two monstrous 200-ton tunnel boring machines that operated from September 2007 until June 2011, chewing through a total of more than 32,000 linear feet of Manhattan bedrock from 63rd Street to 37th Street.

 

View comments or post a comment on this story. (0 Comments)

More News

Feds find ignored safety procedures, fractured safety program led to Amtrak derailment

The train engineer saw equipment and people working on and near track 3 and initiated emergency braking that slowed the train from 106 mph to approximately 99 mph at the time of impact.

Amtrak continues next phase of Penn Station infrastructure work

The railroad is working with NJ TRANSIT and Long Island Rail Road on an overall service plan that minimizes the impact to all New York Penn Station customers to the greatest extent possible.

Alstom to deliver 27 'Jazz' trains to Trenitalia

The delivery is part of an order worth about $198 million.

Commuter rail station named Colo. APWA 'Project of the Year'

It shares signature elements with other Eagle P3 commuter rail stations, such as its glass-and-steel elevator, but custom components make it unique among all other stations — such as its 24 by 14 foot pedestrian underpass.

Alstom to supply signaling, train control for Tel Aviv railway project

The Red Line will begin operations on October 2021, and is planned to service approximately 200,000 passengers every day.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close