MTA to close Sandy damaged tunnels for repairs

Posted on June 5, 2013

Montague Tube image courtesy MTA New York City Transit / Marc A. Hermann
Montague Tube image courtesy MTA New York City Transit / Marc A. Hermann
Two New York subway tunnels heavily damaged by Hurricane Sandy will be closed for long-term repairs this summer, the Metropolitan Transportation Authority announced.

The Greenpoint Tube, which carries the G train under Newtown Creek between Brooklyn and Queens, will be closed for 12 weekends this summer and fall starting July 6. The Montague Tube, an almost mile-long pair of tunnels that carries the R train under the East River between Brooklyn and Manhattan, will be closed for up to 14 months starting the first week in August.

Sandy inundated the tubes with millions of gallons of seawater, which corroded, degraded, or ruined almost everything from tracks and switches, to signals and controls, to power and communications cables. Temporary fixes brought those tunnels back into service, but the damage has led to increased failures of components, a growing number of delayed trains and a pressing need to make permanent repairs.

In the Greenpoint Tube, power cables that were immersed in salt water are corroding from the inside, while corrosion on the outside of rails and fasteners raises the potential for short circuits. The controls for ventilation, lighting and communication systems were destroyed and have not been restored to their pre-Sandy condition.

The Montague Tube is in far worse condition and will require much more extensive repairs. It was flooded for a length of 4,025 feet to a depth of 20 feet with corrosive salt water sitting stagnant in the tube for 10 days. More than 27 million gallons of water were eventually pumped from the tube before work began to make it useable again for train service. While the work was enough to restore R service between Brooklyn Heights and Lower Manhattan, it was never intended to be a permanent repair.

VIDEO: Check out video of MTA officials inspecting the Montague Tube.

View comments or post a comment on this story. (0 Comments)

More News

M-1 Rail opens rail facility for Detroit streetcar

The Penske Tech Center will be the nation’s first vehicle storage and maintenance facility to operate completely off-wire.

Tri-Rail launches train tracking app

The straightforward and user-friendly system superimposes the corridor map on top of a Google map, which shows the precise location of the train.

Alstom to provide additional trainsets for Melbourne rail

The five additional six-car X’Trapolis trainsets will enhance the Melbourne’s Metropolitan Rail Network's capacity.

Honolulu takes delivery of first railcar

The four car train, manufactured by Hitachi Rail Italy, is a key component of the first driverless rail transit system in the U.S.

FRA makes $25M available for rail infrastructure safety upgrades

Applicants can request funds for safety improvements to railroad infrastructure, including railroad crossings, track, tunnels, bridges, yards and other areas.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close