Chicago Red Line project making progress

Posted on July 3, 2013

The Red Line South reconstruction project is among more than $1 billion in investment Mayor Emanuel has directed to improving the backbone of the CTA rail system. Photo by Daniel Schwen
The Red Line South reconstruction project is among more than $1 billion in investment Mayor Emanuel has directed to improving the backbone of the CTA rail system. Photo by Daniel Schwen
Six weeks into the Chicago Transit Authority’s (CTA) Red Line reconstruction project, nearly all of the tracks, ties, third rail and ballast have been removed from the 10 miles of railroad between Cermak-Chinatown and 95th Street, according to officials.

Crews have also begun the rehabilitation of eight of the nine stations that are part of the project, with work including lighting replacement or refurbishment; floor reglazing/repair; painting; cleaning; and new elevators at the Garfield, 63rd and 87th stations. The ninth station, 95th Street Terminal, will be reconstructed in a separate, $240 million project next year.

The Red Line South reconstruction is one of the city’s largest current infrastructure projects and one of the largest transit-related projects in the country. The reconstruction will generate around 1,500 jobs, including 1,000 construction jobs and more than 400 part-time, permanent bus operators. Many of those jobs are being filled by Chicagoans.

Additionally, both of the project’s prime contractors — Kiewit Construction (track work) and F.H. Paschen, S.N.Nielsen (station work) — have either met or exceeded the CTA’s goal for Disadvantaged Business Enterprise (DBE) participation, by hiring a total of 39 DBE subcontractors for a total of $82.5 million. Approximately $54 million of that will go to African-American owned firms.

The Red Line South reconstruction project is among more than $1 billion in investment Mayor Emanuel has directed to improving the Red Line, the backbone of the CTA rail system, providing more than one-third of rail ridership.

Upcoming Red Line projects include the complete reconstruction of the Wilson station ($203M), complete reconstruction of the 95th Street terminal ($240M), and an overhaul of the Clark/Division subway station ($41M).

View comments or post a comment on this story. (0 Comments)

More News

WMATA launches Wi-Fi pilot at six Metrorail stations

The service, part of the GM’s Customer Accountability Report initiatives, will be available for 45 days. After that time, the service will be suspended while the pilot program is evaluated.

Amtrak signs contract with Alstom for new generation, high-speed train

Funding for the trains will come from a $2.45 billion loan via a U.S. DOT railroad rehabilitation program – marking the largest single loan in the agency’s history.

Metra receives final Electric Highliners

Completes 2010's 160-car purchase to outfit the line with a completely new and modern fleet.

Amtrak's microgrid to serve as backup during power outages

In the aftermath of the 2012 Superstorm Sandy, half of the Sunnyside Yard had to rely on portable backup generators for a month due to a damaged transmission line.

Detroit's M-1 begins testing streetcar line

The slow-moving "speeder" vehicle will travel the rail line as part of a testing regimen that ensures the route is free of obstructions.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close