The New York Metropolitan Transportation Authority’s (MTA) Metro-North Railroad issued a 100-Day Report on the Action Plan established by President Joseph J. Giulietti, which focused the railroad’s efforts on improving safety, restoring reliability and improving communications.

Of 32 initiatives established in the Action Plan, 21 have been fully implemented, seven are in progress and two will be pursued after outside entities submit independent reports. Two more initiatives — implementing a “back to basics” plan for train reliability and service delivery and communicating service delivery information to customers and elected officials — will remain ongoing, long-term Metro-North priorities.

“Metro-North has made major strides in the past 100 days, with concrete accomplishments that have made operations safer, established a safety culture, improved service reliability and expanded our communications,” Giulietti said. “Our customers and everyone who relies on Metro-North have seen real accomplishments that have gone a long way toward restoring their faith in the railroad. Our challenge is to keep this relentless focus on improvement that our customers expect.”

Major improvements have been made in many areas including enhancing track inspection and maintenance, installing alerters and video cameras in engineers’ cabs, beefing up the safety and training departments, expanding employee testing programs to ensure understanding of safety rules, creating a computer-based track worker safety system and implementing a Confidential Close Call Reporting System.

The Federal Railroad Administration completed its review of Metro-North practices in May, and its recommendations are incorporated into the 100-Day Report. Two external reports, from the MTA’s Blue Ribbon Panel and the National Transportation Safety Board, have not yet been submitted, but Metro-North has committed to implementing any recommendations from those entities that have not already been addressed.

View comments or post a comment on this story. (0 Comments)

More News

WMATA launches Wi-Fi pilot at six Metrorail stations

The service, part of the GM’s Customer Accountability Report initiatives, will be available for 45 days. After that time, the service will be suspended while the pilot program is evaluated.

Amtrak signs contract with Alstom for new generation, high-speed train

Funding for the trains will come from a $2.45 billion loan via a U.S. DOT railroad rehabilitation program – marking the largest single loan in the agency’s history.

Metra receives final Electric Highliners

Completes 2010's 160-car purchase to outfit the line with a completely new and modern fleet.

Amtrak's microgrid to serve as backup during power outages

In the aftermath of the 2012 Superstorm Sandy, half of the Sunnyside Yard had to rely on portable backup generators for a month due to a damaged transmission line.

Detroit's M-1 begins testing streetcar line

The slow-moving "speeder" vehicle will travel the rail line as part of a testing regimen that ensures the route is free of obstructions.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close