UPDATED: Detroit streetcar facing $12M shortfall

Posted on June 18, 2014

DETROIT — The city’s planned 3.3-mile $137 million M-1 Woodward Avenue streetcar project faces a $12 million funding shortfall and applied for a supplemental $12.2 million from the U.S. Department of Transportation, reported the Detroit News.

The News obtained a two-page letter to Transportation Secretary Anthony Foxx warning the project urgently needs additional grant money to proceed, but said it would survive without the funds, though; it would have to be scaled back. For the full story, click here.

UPDATE: M-1 Rail President/CEO Matthew P. Cullen issued a statement regarding reports the Woodward streetcar system is struggling:

"News reports published today suggested our project is in jeopardy. It is not.

The construction of the M-1 RAIL streetcar will proceed as planned and commence upon City Council approval of our operating agreement. We hope for approval next week.  

We remain very optimistic about the requested TIGER grant based on the quality of our application, the strong support of the Mayor, our congressional delegation and others, the Administration’s focus and commitment to the City of Detroit, and the profound impact of this project for our community. That being said, the TIGER grant is just one component of our funding structure; there are contingency strategies that we will deploy if the grant is not approved."

View comments or post a comment on this story. (0 Comments)

More News

Ill. bill doubles fines for drivers who illegally cross railroad tracks

The legislation doubles the fines from $250 to $500 for a first offense and from $500 to $1,000 for a second or subsequent offense.

FTA's Flowers testifies on D.C. Metro rail safety oversight progress

Through a comprehensive Safety Management Inspection, three Safety Directives, two immediate action letters, and ongoing inspection and investigation activity FTA safety oversight is requiring WMATA to take numerous positive actions to improve safety for passengers and workers.

Siemens consortium to deliver 22 trains to Bangkok

Delivery of the first metro trains is scheduled in 2018, and the order will be completed in the following year.

Sacramento RT considering closing light rail line indefinitely

The agency opened its $44 million Green Line only four years ago; however, the line currently averages only 440 boardings a day with limited service, and costs RT $330,000 annually to operate.

L.A. Metro celebrates launch of Expo Line to Santa Monica

The 6.6-mile Expo extension runs from Culver City to Santa Monica and includes seven stations. Ridership on the new portion is projected to total 18,000 to 20,000 weekday boardings after the first year of service. The travel time from downtown L.A. to the Downtown Santa Monica Station is 48 minutes.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close