Kansas City Streetcar project in the 'home-stretch'

Streetcar construction is on schedule to be completed in fall of 2015. The $102 million 2-mile system will then undergo a period of testing and is anticipated to be open to the public in 2016.

May 13, 2015
Kansas City Streetcar project in the 'home-stretch'

 

2 min to read


Construction of the Kansas City Streetcar remains on schedule and on budget, with all key construction activities at least 70% complete, according to officials.

RELATED:Herzog tapped to operate Kansas City Streetcar

Ad Loading...

"The project is really on the home-stretch," stated Meghan Jansen, public information
manager for KC Streetcar Constructors. "Most of the underground work will be completed
this month. That includes the upgrades to Kansas City's century-old water and sewer
lines."

As of May 1, 2015:
• 71% of track is fully constructed (15,430 feet complete out of 21,771 total feet)
• 96% of water and sewer replacements and upgrades is complete
• 77% of work on the Singleton Yard vehicle maintenance facility is complete
• More than 100 power poles are installed
• First streetcar stop is built at 16th and Main

Streetcar construction is on schedule to be completed in fall of 2015. The $102 million streetcar system will then undergo a period of testing and is anticipated to be open to the public in 2016.

The Downtown Kansas City, Missouri Streetcar project is a two-mile route running  primarily along Main Street connecting Kansas City’s River Market area to  Crown  Center and Union Station. It will serve Union Station, the Cross Roads Art District, the Power and Light District, the city’s central business district, and the historic River Market along with numerous other businesses, restaurants, art galleries, educational facilities, and neighborhoods.

The starter line has  16  stops  spaced  every  two  blocks  and includes  the  Singleton  Yard  Facility  (Vehicle Maintenance Facility) located in Columbus Park. The City forecasts approximately 2,700 will use the streetcar daily once it opens. Riders will not pay a fare, which is intended to minimize dwell times and maximize economic benefits to riders. The  Streetcar will travel in vehicle lanes along Main Street, which is now redesigned to accommodate the Streetcar and minimize delays. Construction has created hundreds of local jobs and spurred millions of dollars of development along the line.

Ad Loading...

(video of Kansas City Streetcar construction from two months ago)

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →