Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Alstom to supply new generation metros to Greater Lyon

The binding part of the order includes the delivery of 30 metros for an amount of $152 million dollars.

Texas' TRE increases frequencies, extends service hours

The new schedule features weekday train service every 30 minutes during peak periods. For evening, mid-day and Saturday service, the frequency will be every 60 minutes.

First Hitachi-made rail vehicles for Miami-Dade unveiled

The Miami-Dade Metro contract amounts to about $300 million dollars representing a total quantity of 68 trains (136 cars).

WMATA report on running red lights calls for capping speeds, brighter bulbs

Plans to upgrade signals with LED bulbs at the following problem-spots by the end of the year: National Airport, Silver Spring, Vienna, Grosvenor, Largo, and Farragut North.

Dallas' rail-connected development driving regional growth, study says

Completed or under-construction TOD near DART stations has already generated $69 million in state and local tax revenue.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment



Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close