Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Stantec named lead designer for Chicago rail modernization program

The $2.1 billion project will reconstruct, modernize and build 1.9 miles of elevated tracks, including bridges and support structures.

London's light rail network to use automatic braking system

Work began on the feasibility of introducing this new safety measure shortly after a tragic crash in Croydon in November 2016.

Trinity Metro begins TEXRail commuter service to DFW airport

The new 27-mile commuter rail line runs from downtown Fort Worth to Dallas Fort Worth International Airport’s Terminal B.

NJ TRANSIT lease plan to generate $2.1M in non-farebox revenue

Continues its efforts to maximize non-farebox revenue by leveraging prime retail locations at its train stations.

MTA averts L Train shutdown to repair Superstorm Sandy damage

The massive reconstruction work, announced in 2016, called for a full closure of the tunnel for 18 months.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation