Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

WSP USA projects recognized with three Calif. transportation awards

The Exposition Line Light Rail in Los Angeles received the California Transportation Foundation's Overall Project of the Year award.

City Council approves transfer of Atlanta Streetcar to MARTA

The $99 million streetcar opened in December 2014 amid sky-high expectations, but ridership failed to meet expectations in its first year and plummeted nearly 60% after the city began charging $1 to ride.

Honolulu officials submit new light rail plan to FTA

The total project cost included in the new plan remains at $8.165 billion for capital costs exclusive of finance charges, with full revenue service scheduled for December 2025.

Alstom to supply traction system in Chengdu, China

The contract is worth approximately $68.3 million. The line is expected to start revenue service by the end of 2019.

Hyperloop One announces 10 winners of 'Global Challenge'

The company will commit meaningful business and engineering resources and work closely with each of the winning teams/routes to determine their commercial viability.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close