Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Bombardier to provide up to 175 trams for Brussels

The first firm order under this framework contract is for 60 Flexity trams and is valued at approximately $206 million.

Toronto's Metrolinx, Airport Authority team to study transit connections

The advancement of work to better integrate transit projects into Canada’s busiest airport will help connect the country’s second largest employment zone and reduce highway congestion.

Study finds untapped development potential around MBTA rail stations

Vacant and underutilized land surrounding 13 Gateway City commuter rail stations could house up to 230,000 residents and 230,000 jobs.

MBTA improves real-time information for subway service

Using more sophisticated data to generate better predictions, and train arrival times are now refreshed every six seconds.

Charlotte's new light rail extension increases rail ridership by 48%

With the opening of the extension, the LYNX Blue Line now connects one side of Charlotte to the other.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close