Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Fla. House pulls high-speed rail safety bill

The bill, which would require high-speed rail companies to install PTC and pay for fencing along section of its tracks where pedestrians could be at risk, was set to be taken up by the state Transportation & Infrastructure Subcommittee but was “temporarily postponed.”

Bombardier to deliver 27 light rail vehicles to Kuala Lumpur

The order from Prasarana Malaysia Berhad is valued at approximately $388 million, with Bombardier's share valued at approximately $266 million.

L.A. Metro add 64 railcars for Red, Purple subway lines

Thirty-four of the new cars, built by China Railway Rolling Stock Corp., will also be used for the Metro Purple Line’s first four-mile extension from the Mid-Wilshire District to Beverly Hills when the line officially opens in 2023.

Poll finds Coloradans favor commuter rail over commuter bus

If passed, House Bill 17-1242 is projected to generate $700 million for new transportation infrastructure in Colorado.

Valley Metro extends 5-year rail service contract with ACI

The company began service operations for Valley Metro Rail prior to the opening in December 2008 and has expanded from the original 20 miles to include six new miles of extensions in 2015 and 2016.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close