Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Calif. wine train owners consider offering commuter service

A commuter train would be designed to take off the road at least some of the 25,000 to 68,000 vehicles that travel various sections of Highway 29 each day.

Chicago Union Station redevelopment plan receives fed assistance

The USDOT Build America Bureau and the City of Chicago are entering into an EmPA agreement, under which Chicago can work closely with USDOT with the ultimate goal of seeking up to $1 billion in federal funding for the project.

L.A. Metro recommends Tutor Perini/O&G for Purple Line project

The company has delivered subway tunnel projects for the Central Subway project in San Francisco, the University Link in Seattle and the East Side Access project in New York. 

Hyperloop Transportation Tech. to explore Czech Republic links

This is the first Hyperloop agreement to connect two international cities.

CFO Graham appointed president of rail supplier Brookville

Upon joining the company in October 2015, Graham brought with him two decades of financial leadership from a variety of industries, including manufacturing, distribution, and healthcare.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close