Calif. HSR lawsuit delays cost $63 million, 17 months

Posted on June 15, 2016

Central Valley construction photo from February 2016. California High Speed Rail Authority
Central Valley construction photo from February 2016. California High Speed Rail Authority

SACRAMENTO, Calif. — Another $63 million was added to the cost of California's high-speed rail project and the completion date for the first 29-mile leg was pushed back 17 months to August 2019, after the state won a lawsuit that had tied up land needed for construction for four-and-a-half years on Tuesday, Deseret News reported.

Landowners in the Central Valley sought to block the controversial $64 billion project there, but a Sacramento County Superior Court judge ruled in March that plans for the system do not violate promises made to voters who approved selling nearly $10 billion in bonds for the project, according to the report.

The lawsuit had tied up access to financing and officials said nearly 500 appraisals for land along the route became outdated during that time. Officials said the additional cost would come from a $160 million reserve, which was included in its original $985.1 million contract with construction consortium Tutor Perini-Zachry-Parsons, Deseret News reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Proposed downtown L.A. streetcar gets big boost

Supporters say ridership on the 3.8-mile service could reach 6,000 people per day.

Wabtec completes majority ownership of Faively Transport

The combination creates one of the world's largest public rail equipment companies, with revenues of about $4.2 billion and a presence in all key transit and freight rail markets worldwide.

Bombardier plant hosts royal visit from HRH The Duke of Cambridge

During his visit, His Royal Highness was given a site tour and inspected the company's assembly of Elizabeth line trains, where he met manufacturing, welding and painting apprentices.

Mich. State railway management certificate program updates offerings

The updated program treats the railway as a system, covering freight supply chain integration and efficient/value-added transportation of passengers.

WMATA proposes cutting late night rail service

Additionally, the earliest trains on Sunday would start at 8 a.m., while the start times for trains on weekdays and Saturdays would remain at 5 a.m. and 8 a.m., respectively.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close