NYC Transit to shut down L train tunnel for 18 months
The decision to do the work under a full tunnel closure, instead of a one-track, three-year closure, was made based on a detailed operational review. The tunnel was severely damaged during Superstorm Sandy.
MTA New York City Transit (NYCT) announced that the massive reconstruction work needed to the Canarsie Tunnel, which carries the L train under the East River between Brooklyn and Manhattan, will require a full closure of the tunnel for 18 months starting no sooner than 2019.
The decision to do the work under a full 18-month tunnel closure, instead of a one-track, three-year closure, was made based on a detailed operational review, and only after significant community engagement to consider all adverse impacts, according to the agency. Serious consideration was also given to consequences of unplanned outages that would occur if one track was closed for three years.
Ad Loading...
“While the MTA always looks to avoid service disruptions, there is no question that repairs to the Canarsie Tunnel are critical and cannot be avoided or delayed. Throughout this process we have committed to engaging the community and listening to all concerns so that we can address them as we prepare for this necessary work,” MTA Chairman/CEO Thomas F. Prendergast said.
Since May, the MTA has held four large-scale, interactive community meetings in communities affected by the upcoming closure, which were led by Prendergast, NYCT President Veronique “Ronnie” Hakim, Chief of Operations Planning Peter Cafiero, and Sr. VP for Capital Program Management John O’Grady.
MTA officials also visited all 11 Community Boards along the L Line, which were overwhelmingly in favor of the full, shorter-duration closure. Of the comments MTA received directly through email, social media and at meetings, 77% were in favor of the full, shorter closure.
“We think it is better to have a shorter duration of pain than a longer more unstable process — and risk unplanned closures — by leaving one track open during construction,” Hakim said.
The Canarsie Tunnel was one of nine underwater tunnels that flooded during Superstorm Sandy, all of which required major rehabilitation and repair. Some of that work was accomplished during night and weekend closures, while the R line’s Montague Tunnel under the East River was closed for 13 months and the G line tunnel under Newtown Creek was closed for two months, both for complete renovations.
Ad Loading...
The Canarsie Tunnel suffered extensive damage to tracks, signals, switches, power cables, signal cables, communication cables, lighting, cable ducts and bench walls throughout a seven-mile long flooded section of both tubes. Bench walls throughout those sections must be replaced to protect the structural integrity of the two tubes that carry trains through the tunnel.
Operation Lifesaver awarded $220,200 in grants to 12 states to support rail safety campaigns focused on grade crossing awareness and trespass prevention.
The survey showed that commute trips still make up the majority of ridership, with most riders boarding 2 to 3 days a week, reflecting hybrid work schedules. Two-thirds of Caltrain riders have access to a car, while 37% of Caltrain riders are considered low-income.
Advances in data and analytics are giving transit agencies new opportunities to refine maintenance practices, improve efficiency and make more informed decisions about asset performance.
In this Consultant Roundtable, Carmen C. Cham shares insights on how agencies can create spaces that are intuitive, connected and built for long-term impact.
The Red Line Extension Project will provide the Far South Side of Chicago with rapid rail transit for the first time by extending the Red Line by 5.5 miles from 95th Street to 130th Street, including the construction of four new Red Line stations at 103rd, 111th, Michigan, and 130th streets.
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
While recognizing regional economic constraints and continuing to improve service, the budget increases the jurisdictional subsidy to less than 1.8%, significantly below the inflation rate and the 3% regional target, said agency officials.
With more than 59,400,000 boardings since the service’s debut, the A Line’s utilization surpassed that of all other RTD rail services in 2025, the agency reported.
The plan outlines funding for transit operations, capital projects, and freight and passenger rail initiatives, as state officials seek public input on priorities shaping mobility and infrastructure across the Commonwealth.