Alstom's Citadis begins dynamic testing on Ottawa's O-Train line
During this phase of the project, the trains will undergo various tests, including dynamic testing at speeds of approximately 50 mph up to approximately 62 mph.

Rideau Transit Group

Alstom’s Citadis Spirit, a 100% low-floor light rail vehicle designed for North America, began dynamic testing on the O-Train Confederation Line in Ottawa. Ottawa’s future light rail vehicles will be tested both at the Belfast Yard Storage and Maintenance Facility (Belfast Yard), as well as along approximately four mile of test track.
During this phase of the project, the trains will undergo various tests, including dynamic testing at speeds of approximately 50 mph up to approximately 62 mph. The dynamic tests that will take place on the test track will focus on traction and braking performance, train behavior, and the comfort and performance of the bogies.
Static testing will take place at Belfast Yard and will validate function performance, including HVAC, doors, lighting, passenger information, and on board data systems. This phase of testing will run through to the end of March 2017, during which more than 50 test procedures will be completed. Upon completion of this first series of tests, more than a dozen tests will be conducted on a multiple unit train, i.e. two trains coupled together.
“The commencement of dynamic testing marks the first 100% low floor vehicle to enter validation testing in Ontario and brings the Citadis Spirit one step closer to the start of commercial service in the City of Ottawa. This rigorous testing of the trains will ensure smooth and safe operation for both the operators and passengers alike,” said Angelo Guercioni, managing director for Alstom, Canada.
Alstom is supplying 34 Citadis Spirit light rail vehicles for the O-Train Confederation Line, and will maintain both the vehicles and the line’s infrastructure for a period of 30 years. This first phase of the O-Train Confederation Line comprises 13 stations along an approximate 7.8 mile route. The O-Train Confederation Line is expected to begin full revenue service in 2018.
Thanks to its modular design, the Citadis Spirit provides for a very flexible manufacturing process. The Citadis Spirit is being assembled by a local workforce at Belfast Yard, creating over 100 jobs in the Ottawa area, with the support of an established supply chain of over 60 Canadian suppliers to meet the 25% Canadian content requirement. In addition to vehicle assembly in the Ottawa area, the Alstom manufacturing facility in Sorel-Tracy, Quebec is assembling the bogies for the Citadis Spirit.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →