FTA releases WMATA traction power report, issues safety directive

The special directive is based on 22 findings from an FTA investigation report into the condition and safety performance of the Metrorail TPE system, which was also released on Friday.

December 9, 2016
FTA releases WMATA traction power report, issues safety directive

Mariordo

4 min to read


Mariordo

The Federal Transit Administration (FTA) issued Special Directive 17-1 to the Washington Metropolitan Area Transit Authority (WMATA) requiring the transit agency to complete 47 actions to correct deficiencies in its traction power electrification (TPE) system, which is used to electrify Metrorail trains.

The special directive is based on 22 findings from an FTA investigation report into the condition and safety performance of the Metrorail TPE system, which was also released on Friday.

Ad Loading...

“The safe operation of Metrorail service is directly dependent on WMATA implementing corrective actions to reduce and eliminate electrical arcing events that have too often resulted in smoke and fire, which can endanger passenger safety,” said U.S. Transportation Secretary Anthony Foxx. “WMATA has already started to address these issues, and the FTA report and special directive will help WMATA prioritize what it must do to improve its traction power system to keep the trains running safely.”

The investigation report finds that while the traction power system continues to be a concern, FTA safety oversight leadership has driven WMATA to create a safer environment for both workers and passengers. In May 2016, FTA directed WMATA to complete repairs to its TPE system on segments of the Red Line where a large number of electrical arcing events resulted in smoke and fire. As a result of WMATA’s subsequent maintenance activity, the number and severity of these events has been reduced. WMATA experienced 18 electrical arcing events in these areas from March 1 to June 14 of this year, including four major events at the end of April and early May. Since June 15, there have been only eight relatively minor events.

Since the FTA assumed temporary safety oversight of the Metrorail system in October 2015, WMATA has reported more than 70 safety events resulting from electrical arcing in its traction power system. Each of these events required an emergency response, and many resulted in the partial or full shutdown of a station or off-loading of a passenger train.

Given the sharp increase in the number of TPE system-related failures and events over the last year, this FTA investigation focused on four categories of safety critical concerns: (1) TPE System Roles, Responsibilities, and Resources; (2) TPE Infrastructure; (3) Testing and Inspection Programs; and (4) Capital Projects.

NCinDC_Flickr

The FTA investigation confirmed that the safety performance of WMATA’s traction power system has deteriorated with age, deferred maintenance, and increased exposure to water and other contaminating materials. The FTA report also finds that key components of the TPE system have been compromised and are no longer performing as originally specified, and that programs to replace and upgrade critical TPE-related infrastructure have not been sufficient for the age of the system or the demand placed on it.

Ad Loading...

In addition, the FTA report finds that in response to changing budgetary and staffing conditions, WMATA eliminated preventive maintenance programs to test key traction power components to predict failures, eliminated or cut back cleaning programs in tunnels, and limited its corrosion control testing program.

Over the last year, WMATA has already taken a number of critical steps to address deficiencies within its traction power system. For example, WMATA has nearly completed a program to ensure that its power cable connector assemblies are properly constructed and installed, enhanced its visual and thermal cable inspection program, eliminated third rail expansion joints in tunnels, and reinstated its tunnel and insulator cleaning programs. WMATA is also reviewing roles and responsibilities for inspecting, testing, and maintaining system elements, and created a new department with exclusive responsibility for high voltage TPE system maintenance.

Building on this progress, and as directed by Special Directive 17-1, WMATA must develop corrective action plans to address the findings of the report and related required actions. WMATA’s proposed corrective action plans are subject to FTA approval, and the FTA will monitor the agency’s progress to implement the safety improvements.

The traction power report, along with other FTA-issued investigation reports, demonstrates how the FTA is exercising the authority and enforcement tools provided by Congress to aid WMATA in addressing systemic safety deficiencies and building a strong safety culture. It is important to note that the FTA’s reports do not amount to a finding that the Metrorail system is “unsafe.” In each investigation and report, and with each step taken, the FTA assessed the risk associated with the flaws found in the Metrorail system, and determined that those risks are not so great that they place passengers and workers at substantial risk of death or injury.

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →