METRO Magazine Logo
MenuMENU
SearchSEARCH

Caltrain negotiates extension for electrification project

While the agency awaits a decision from the FTA about the execution of a $647 million funding agreement.

March 1, 2017
Caltrain negotiates extension for electrification project

 

3 min to read


Caltrain announced that it has negotiated an extension of the deadline for contractors to begin construction of the Peninsula Corridor Electrification Project while the agency awaits a decision from the Federal Transit Administration about the execution of a $647 million funding agreement.

The contractors agreed to extend the deadline for four months, from March 1 to June 30. Last week, FTA announced that execution of the grant would be delayed until the President makes decisions about the availability of funds in the Administration’s upcoming budget proposal to Congress. The extension is needed to preserve the electrification project’s contracts during this time. 

Ad Loading...

The extension does not come without cost implications. Buying additional time from the contractors will likely require the utilization of up to $20 million in project contingency that otherwise would have been available for construction related expenses in the future. The sooner the grant agreement is executed, the smaller the impact will be to the project’s contingency.

Caltrain has been working with the FTA since 2009 to ensure that the project meets all of the rigorous statutory and regulatory requirements of the Core Capacity competitive discretionary program. The project was rated highly after thorough evaluation including ridership studies, design assessments, financial analyses and cost benefit evaluations by the FTA and the U.S. Department of Transportation (USDOT). Caltrain, as the project sponsor, also has significant local financial support for this project, demonstrated by the project’s substantial leveraging of local, state and regional funds. 

The federal Core Capacity request makes up only 32% of the total project cost.
Caltrain officials expressed their gratitude to their primary modernization contractors for providing additional time and flexibility to manage the unforeseen delay.

“Every project that has achieved these milestones has received an executed Full Funding Grant Agreement and we don’t expect that this project will be any different,” said Caltrain Executive Director Jim Hartnett.

In September 2016, Caltrain awarded contracts to Balfour Beatty for construction of the corridor’s electrification infrastructure, and to Stadler US Inc. for the manufacture and delivery of high-performance electric commuter rail trains that will increase the system’s ridership capacity and connect Peninsula communities with more frequent service and improved travel times. The contractors have advanced the project’s design and were scheduled to begin construction before FTA announced the delay.

Ad Loading...

“This project will not only transform the aging diesel system into a modern and efficient electric commuter rail system better serving the needs of the region but it will also be the driving force for the creation of a new railcar production facility in the U.S., that will employ several hundred workers,” said Martin Ritter, Stadler US CEO.

Caltrain cautioned that additional extensions may not be possible. “Our contractors have agreed to delay construction for the maximum amount of time possible,” said Hartnett. “Delaying a decision on Federal funding beyond June 30 will be the same as rejecting the grant.”

More Rail

A New York MTA subway car with an open gangway
Railby Staff and News ReportsSeptember 16, 2026

New York MTA Advances Final Contract for Second Avenue Subway Expansion

Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.

Read More →
A San Diego MTS Copper Line vehicle
Railby Staff and News ReportsSeptember 15, 2026

San Diego MTS Breaks Monthly Trolley Ridership Record

Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.

Read More →
NJ TRANSIT's new Multilevel III commuter railcar manufactured by Alstom
Railby Alex RomanSeptember 14, 2026

Report Examines NJ TRANSIT Reliability, Funding Challenges

The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.

Read More →
Ad Loading...
A CapMetro commuter rail train provided by Stadler
Railby Staff and News ReportsSeptember 11, 2026

Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement

Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.

Read More →
Rendering of an Alstom train in a VIA Rail Station
Technologyby Alex RomanSeptember 10, 2026

Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More

In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.

Read More →
The CATS Gold Line in service with the city skyline in the background.
Railby Staff and News ReportsSeptember 3, 2026

CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips

With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.

Read More →
Ad Loading...
Designing Stations Around the Passenger
RailSeptember 2, 2026

Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations

Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.

Read More →
Amtrak Sunnyside Groundbreaking
Railby Staff and News ReportsSeptember 2, 2026

Amtrak Begins Major Construction at New York’s Sunnyside Yard

The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.

Read More →
O'Hare Flyer Rendering
Railby Staff and News ReportsAugust 27, 2026

Chicago Leaders Unveil Plans for O’Hare Airport Express Train

The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.

Read More →
Ad Loading...
An OCTA coastal rail line train.
Railby Staff and News ReportsAugust 27, 2026

OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor

The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.

Read More →