Rail

LA Metro rail extension project marks tunneling milestone

Posted on December 12, 2017

The $1.75-billion Regional Connector Transit Project is a 1.9-mile underground light-rail extension that will connect the Blue, Expo, and Gold Lines in downtown Los Angeles and will include three new stations at 1st Street/Central Avenue, 2nd Street/Broadway, and 2nd Place/Hope Street.
Screenshot
The $1.75-billion Regional Connector Transit Project is a 1.9-mile underground light-rail extension that will connect the Blue, Expo, and Gold Lines in downtown Los Angeles and will include three new stations at 1st Street/Central Avenue, 2nd Street/Broadway, and 2nd Place/Hope Street.
Screenshot

Angeli, the Tunnel Boring Machine (TBM) mining twin tunnels for LA Metro’s Regional Connector Transit Project, achieved another major milestone when she broke through a wall of dirt at the underground Grand Avenue Arts/Bunker Hill Station at 2nd and Hope in downtown Los Angeles, after being re-launched to start the second tunnel near Little Tokyo earlier this summer.

Angeli was lowered into the ground near 1st and Central in late 2016 and began digging the tunnels in early February. In June, the TBM completed digging the first of two tunnels. The machine will now be repositioned to begin tunneling the last segment of the tunnel to 4th Street and Flower. Tunnel mining operation is expected to be complete in mid-January 2018.

The $1.75-billion Regional Connector Transit Project is a 1.9-mile underground light-rail extension that will connect the Blue, Expo, and Gold Lines in downtown Los Angeles and will include three new stations at 1st Street/Central Avenue, 2nd Street/Broadway, and 2nd Place/Hope Street.

 

The rail line is expected to serve 88,000 riders daily — including 17,000 new riders — and save commuters up to 20 minutes by reducing the need to transfer. The connector will provide a one-seat, one fare ride for commuters from Azusa to Long Beach and from East Los Angeles to Santa Monica. The project is scheduled to be completed in 2021.

View comments or post a comment on this story. (0 Comments)

More News

Alstom debuts world's first hydrogen train entering passenger service

The zero-emission Coradia iLint, which debuted in Lower Saxony, Germany, can reach up to 140 km/h (90 mph).

WMATA announces contracting opportunity for Silver Line extension

Under the agency's plan to "Keep Metro Safe, Reliable and Affordable," the use of competitive contracting is recommended as a way to control operating and maintenance costs

Amtrak Pacifc Surfliner, MLB team up for rail safety awareness

Partners with San Diego Padres, Los Angeles Angels and California Operation Lifesaver to highlight the importance of safety around train tracks.

Zmudzinski to lead national rail systems at WSP

Will lead the firm’s transit and rail systems engineering team and support business development across the U.S.

4 teams submit design-build bids for Foothill Gold Line light rail project

Includes technical approach to completing the design and construction of the project, their management method, and financial bid.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation