Railroads warn of widespread shutdowns unless PTC deadline extended

Posted on October 20, 2015

NTSB officials at the site of the Amtrak train #188, which derailed outside of Philadelphia in May 2015. Photo: NTSB/Cassandra_Johnson
NTSB officials at the site of the Amtrak train #188, which derailed outside of Philadelphia in May 2015. Photo: NTSB/Cassandra_Johnson

WASHINGTON, D.C. — Major rail companies on Monday intensified their demands that Congress give them more time to roll out positive train control technology — or warned that they could face major service shutdowns around the country, the Pittsburgh Post-Gazette reported.

The freight rail industry needs until the end of 2018 to install the necessary hardware and until the end of 2020 to have it fully tested and operational, said Ed Hamberger, president and CEO for the Association of American Railroads, the report said.

“There will be a transportation crisis in this country,” said Michael Melaniphy, president and CEO of the American Public Transportation Association.

According to Melaniphy, an orderly shutdown of a major rail network takes about eight weeks. Without an extension by the end of October, many freight and commuter rail companies will likely begin discussing service shutdowns, the Post-Gazette reported. For the full story, click here.

View comments or post a comment on this story. (0 Comments)

More News

Calif. bill requires human trafficking training for public transit agencies

Measure would amend an existing law that does not require training on the topic.

Metra marks completion of major PTC milestone

Chicago is the most complex railroad network in the country, with 1,300 to 1,400 trains operating over multiple railroads every day.

L.A. Metro releases new 'Metro Manners' etiquette campaign videos

Features a pop star super hero character who battles a monster who blatantly violates etiquette rules on the transit system.

FRA makes $46M available for PTC work

The NOFO represents the balance of the $250 million Consolidated Rail Infrastructure and Safety Improvements Program funds available. 

NJ Transit begins 4-month shutdown of line for PTC repairs

Expanded local and express bus service is being offered for Atlantic City Rail Line user until service returns in January.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation