WMATA has accepted and placed into service 548 of the railcars, which will need to be taken out of service and replaced in phases.
WMATA
1 min to read
WMATA has accepted and placed into service 548 of the railcars, which will need to be taken out of service and replaced in phases.
WMATA
WASHINGTON, D.C. — Following a new internal review, the Washington Metropolitan Area Transit Authority has to replace faulty wiring on every one of its new 7000-Series railcars, WTOP reports.
Since the cars first went into production in 2012, wire crimping has never been done properly, a review by WMATA’s Quality Assurance, Internal Compliance, & Oversight office found, which contributed to incidents where railcars have problems that can create significant delays.
Ad Loading...
WMATA has accepted and placed into service 548 of the railcars, which will need to be taken out of service and replaced in phases.
From the beginning, WMATA failed to require that the car manufacturer, Kawasaki, perform appropriate quality checks and provide engineering design support, the review found. The contract for the cars also failed to provide specific consequences for failing to provide certain work that measured up to standards. For the full story, click here.
BRIT patrols are over and above those already occurring within the district. For example, the agency experienced three copper wire thefts along the G Line in April, followed by others later in the month and in early May.
Today’s riders—and the communities you serve—expect more from public transit. While ADA compliance is required, leading transit agencies know that true accessibility also means delivering dignity, efficiency, and a better rider experience. This whitepaper reveals why forward thinking agencies nationwide choose the Low Floor Frontrunner as their first choice for ADA compliant vehicles—setting a new standard with passenger first design, faster boarding, improved safety, and unmatched operational performance.
Fred Ferguson, president and CEO of the American Bus Association (ABA), discussed how the industry prepares for emergencies, the growing recognition of motorcoaches as critical infrastructure, and steps operators can take to strengthen disaster readiness.
The approved contract modification will increase funding for transit security officer services to a total not-to-exceed amount of $32.1 million, ensuring a continued and visible security presence across DART’s buses, trains, stations, and facilities.
The Siemens CBTC System, Trainguard MT, in compliance with New York Subway Interoperability Interface Specifications, enables trains to run as close as 90 seconds apart, using next-generation signaling and continuous communication to keep operations moving seamlessly.
According to the new quarterly data, there were double-digit reductions in five of the eight serious crime categories, including aggravated assaults and robberies.
The project, finalized on February 12, provides the city with two different configurations of high-definition cameras to outfit 16 buses in the Pretzel City Area Transit fleet.