Boston's Commuter Rail Revived Through Rehab
Since Keolis began operation of the commuter rail system, it has worked with the MBTA to revitalize its aging fleet, improve track and infrastructure, and boost revenue and ridership.

The Commuter Rail Maintenance Facility serves as the primary shop for maintaining and repairing the fleet of 410 coach cars and 90 locomotives.
Photos via Janna Starcic

In July 2104, Keolis Commuter Services (KCS) was awarded an eight-year contract to operate and maintain the Boston-based Massachusetts Bay Transportation Authority's (MBTA) commuter rail system. It is part of a public transport system which also includes bus, metro, trams, and ferries. Since Keolis began operation of the system, it has worked with the MBTA to revitalize its aging fleet, improve track and infrastructure, and boost revenue and ridership.
Challenges to overcome
■ Once Keolis took over the contract, the company began assessing challenges, which included working with a diverse, aging rolling stock fleet that was overdue for overhaul. The unreliable rolling stock combined with poor operational techniques led to decreased system reliability. “The infrastructure suffered from decades of underinvestment and the fleet was also in a very poor state of repair,” says David Scorey, GM/CEO of KCS.
Additionally, union contract rules were outdated and inconsistent with industry norms. According to Scorey, the culture hadn’t evolved in decades, and workforce was not engaged. To that end, Keolis brought in experience and best practices from an international pool to implement their approach. Use of data analysis and action plans have blended really well with action in the field, Scorey explains. “We have made real progress.”
The network was also increasingly paper driven, Scorey adds. Keolis deployed an asset management data system to build historical data on which trends, costs, and labor hours could be planned and based. To improve accountability, shop management was consolidated. The company also introduced Lean Management Techniques in the production shops. In keeping with the implementation of innovative practices and technologies, KCS launched a technologically advanced time clock system that uses biometric scanning to improve the accuracy and ease of timekeeping processes at all Keolis mechanical facilities. The system, in use since 2016, enables employees to clock in and out by swiping their finger and tapping in a personalized PIN number, replacing a badge system.
Maintenance, Operations
■ The Commuter Rail Maintenance Facility serves as the primary shop for maintaining and repairing the commuter rail’s fleet of 410 coach cars and 90 locomotives. Here, coach cars can undergo full overhauls or rebuilds in addition to in-house air brake repair, HVAC repair, and cleaning. The locomotive shop has five tracks for light to medium repairs and partial overhauls. The facility employs 275 employees working three shifts, which results in 22 train-sets serviced and repaired per day.
Keolis’ Cobble Hill railroad operations facility, located in Somerville, Mass., is a multi-functional commuter rail operations center staffed around the clock. It is home to four departments, including training, safety, engineering, and dispatchers. The facility houses the Keolis Emergency Operations Center, a new simulation lab and a number of classrooms and training tools. It employs 140 personnel and is charged with train dispatching for the north side of the network. Additionally, 60 monthly employee training classes are offered at this location.

Locomotive overhaul
■ In March of this year, Boston MBTA’s Fiscal and Management Control Board voted to exercise a contract option to initiate the overhaul of 27 additional commuter rail locomotives. Under an existing contract, the MBTA is in the process of overhauling 10 F40 models of the so-called “legacy fleet” of

commuter rail locomotives. The additional overhauls are part of a strategy to improve locomotive reliability in the near term while simultaneously studying ways in which the entire commuter rail network can function in the future.
Originally approved in June 2017, the ongoing contract with Motive Power Inc. returned the first of the overhauled F40s to passenger service in March 2019. The second F40 recently returned to service, while the remaining eight will return on a rolling basis with the all 10 expected to return by the end of August 2019.
The program consists of completely rebuilding and refurbishing the F40 models with additional upgrades, including remote monitoring and diagnostics, forward-facing and cab cameras, and modern brake and control systems.
Other key accomplishments that have been realized since Keolis took over operation of the commuter rail service includes the signing of a revenue-sharing agreement with the MBTA in 2017 that incentivizes ridership growth and modernizes fare collection practices to reduce fare evasion. And, in addition to introducing the MBTA commuter rail app, which is aimed at reducing overcrowding and providing live service alerts, Keolis began using a drone system to help engineers conduct infrastructure inspections.
According to company officials, KCS is performing more repair and capital work on both the network and rolling stock than ever before. On-time performance was 89% in 2017, two points above the previous 10-year average. On average, there are 28 more coaches available daily compared to 2014. In terms of punctuality, KCS is operating 10,000 more scheduled trains annually compared to 2014. In the second quarter of 2018, 96% of trains arrived within 10 minutes of their scheduled time, the highest level in the past four years, according to company data.
More Rail

Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →
Alstom Acquires Delaware Site to Support Amtrak NextGen Acela Fleet
The company is investing more than $55 million to acquire and improve the property and will employ approximately 100 people at this site once it is operational.
Read More →
When Routine Fails: How Public Transit Must Adapt for the World Cup
The 2026 FIFA World Cup will test transit agencies’ ability to manage unpredictable travel patterns, making real-time data and operational flexibility critical to moving millions of visitors efficiently.
Read More →
California Selects Team for Nation’s First True High-Speed Rail Track and Systems Contract
The board action follows completion of track installation at the 150-acre southern railhead in Kern County, which will serve as the staging and distribution hub for high-speed track and systems installation.
Read More →
Seattle's Sound Transit Launches New Sounder Railcars into Service
Alstom manufactured all the cars under a $46.5 million contract and came into service in anticipation of summer crowds for soccer and baseball.
Read More →
Alstom Partners With Universities to Build Rail Talent Pipeline
The partnerships include a new engineering scholarship fund at Alfred State College in Western New York and collaborations with transportation centers at the University of Pennsylvania and New York University.
Read More →
Chicago's NITA Act Moves Into Next Phase as Service Improvements Begin
Rider-focused improvements will begin rolling out across the system immediately as CTA, Metra, and Pace increase service this summer in the six-county region.
Read More →