Chicago Transit to reconstruct rail line

Posted on June 6, 2012

Chicago Transit Board Chairman Terry Peterson and Chicago Transit Authority (CTA) President Forrest Claypool announced the complete reconstruction of the South Red Line from Cermak-Chinatown to 95th Street.

The project, one of the biggest CTA construction projects in its history, will completely rebuild the tracks and track bed on the 10-mile stretch of the Red Line known as the Dan Ryan Branch.

“Once this work is complete, our customers will be riding on a brand-new railroad. Their commutes will be faster, their rides will be smoother and more comfortable, and they’ll see fewer service interruptions thanks to better reliability,” said Claypool.

In spring 2013, CTA will close the South Red Line from Cermak-Chinatown to 95th Street for five months, affecting nine stations. To ease the impact on riders, CTA plans to offer multiple commuting options during this phase of the project.

“We realize this will have an impact on our customers,” Peterson said. “That’s why we are planning to offer multiple, convenient options for people to get around during the construction. Our No. 1 goal will be to make sure that we provide travel options for our customers so that they can get where they need to go.”

The five-month construction option will save $75 million over an option to perform work on weekends only. That $75 million savings will be reinvested into station upgrades along the South Red Line, such three new elevators, lighting, painting, electrical substation work and other improvements, and will also enable CTA to provide the extensive alternative service during construction.

Built in 1969, the South Red Line tracks are well beyond their expected lifespan. Despite ongoing repairs and maintenance, around 40% of the branch includes slow zones — where trains travel well below the designed speed limit. In some cases, Peterson said, trains that would normally travel up to 55 mph are instead running at 15 mph. The reconstruction will shave 20 minutes off the round-trip between 95th Street and Roosevelt, according to officials.

The work will replace all the ties, rails, third rail, drainage systems and ballast. The nine stations along the branch will receive improvements ranging from new lighting and paint to new bike racks. Elevators will be added at Garfield, 63rd and 87th Streets, making the entire South Red Line accessible.

More information about the project is available here.

View comments or post a comment on this story. (0 Comments)

More News

Metra adds state funding for 2 new rail stations

The two stations have been planned for years, however, funding was first held up in the state’s budget woes and then cut in 2017.

Report suggests Cleveland should replace entire rail fleet by 2028

While both fleets have had some level of mid-life rehabilitation, each fleet is exceeding the acceptable 30-year useful life for railcars.

Valley Metro rail extension gets FTA approval to enter engineering

The approval moves the project forward in the capital grants program.

Sound Transit rail extension moves into next phase

In the coming months, the agency will continue intensive work to advance its federal grant application.

Senators threaten to withhold WMATA funds if it selects Chinese railcars

CRRC is actively pursuing a WMATA contract likely to exceed $1 billion to build up to 800 of its new 8000-series railcars.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation