Chicago Red Line project making progress

Posted on July 3, 2013

The Red Line South reconstruction project is among more than $1 billion in investment Mayor Emanuel has directed to improving the backbone of the CTA rail system. Photo by Daniel Schwen
The Red Line South reconstruction project is among more than $1 billion in investment Mayor Emanuel has directed to improving the backbone of the CTA rail system. Photo by Daniel Schwen
Six weeks into the Chicago Transit Authority’s (CTA) Red Line reconstruction project, nearly all of the tracks, ties, third rail and ballast have been removed from the 10 miles of railroad between Cermak-Chinatown and 95th Street, according to officials.

Crews have also begun the rehabilitation of eight of the nine stations that are part of the project, with work including lighting replacement or refurbishment; floor reglazing/repair; painting; cleaning; and new elevators at the Garfield, 63rd and 87th stations. The ninth station, 95th Street Terminal, will be reconstructed in a separate, $240 million project next year.

The Red Line South reconstruction is one of the city’s largest current infrastructure projects and one of the largest transit-related projects in the country. The reconstruction will generate around 1,500 jobs, including 1,000 construction jobs and more than 400 part-time, permanent bus operators. Many of those jobs are being filled by Chicagoans.

Additionally, both of the project’s prime contractors — Kiewit Construction (track work) and F.H. Paschen, S.N.Nielsen (station work) — have either met or exceeded the CTA’s goal for Disadvantaged Business Enterprise (DBE) participation, by hiring a total of 39 DBE subcontractors for a total of $82.5 million. Approximately $54 million of that will go to African-American owned firms.

The Red Line South reconstruction project is among more than $1 billion in investment Mayor Emanuel has directed to improving the Red Line, the backbone of the CTA rail system, providing more than one-third of rail ridership.

Upcoming Red Line projects include the complete reconstruction of the Wilson station ($203M), complete reconstruction of the 95th Street terminal ($240M), and an overhaul of the Clark/Division subway station ($41M).

View comments or post a comment on this story. (0 Comments)

More News

Dallas' D2 subway reaches preliminary design milestone

The next phase is preparing a supplemental draft environment impact statement to access potential impacts and benefits of the project.

Bombardier temporarily ceases work at its Canadian facilities

The suspension includes Bombardier’s aircraft and rail production activities in the provinces of Quebec and Ontario.

Sound Transit completes downtown light rail service

The return follows the conclusion of Connect 2020, an 11-week period of major service impacts while construction crews connected the existing system in downtown Seattle to East Link.

FRA seeks to gauge performance, service of intercity passenger rail

The rule would define Amtrak on-time performance and would set forth a minimum on-time performance standard of 80%.

Calif.'s Metrolink lands $10.7M CRISI grant

The grant will partially fund the Burbank Corridor Speed and Safety Improvements Project, which will enhance service on Metrolink’s Ventura County and Antelope Valley lines.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation