Rail

L.A. Metro begins tunneling on first section of Purple Line extension

Posted on October 17, 2018

Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega.
L.A. Metro
Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega.
L.A. Metro
In a major milestone for construction of the first section of the Metro Purple Line Extension Project, the Los Angeles County Metropolitan Transportation Authority (Metro) began tunneling work underneath Wilshire Boulevard and La Brea Avenue. 

Twin tunnel boring machines (TBMs), named Elsie and Soyeon, will begin by tunneling parallel underground sections between the future Wilshire/La Brea Station and the current Wilshire/Western Purple Line terminus. The TBMs each weigh 1,200 tons, are 450 feet long, have a diameter of 21.8 feet, and will simultaneously be excavating approximately 60 feet per day in the twin tunnels over the next two years.

The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet. The two machines will be separated by about 16 feet of soil as their giant cutter heads spin to grind away the soil in their path. Meanwhile, hydraulic arms at the rear of the machines are inserting concrete segments into the newly mined tunnels, which also help propel the machines further forward.

Metro broke ground on the 3.92-mile first section of the project in November 2014 that will begin at the existing Wilshire/Western Station and continue to new stations that are being excavated at Wilshire/La Brea, Wilshire/Fairfax, and Wilshire/La Cienega. The $2.82-billion project section is funded by Measure R and federal funds. Stantec will lead management of the construction of this section.

The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet.
L.A. Metro
The TBMs will work in tandem, with Elsie expected to trail her sister by about 150 feet.
L.A. Metro

The first section of the Purple Line Extension Project is scheduled to be operational in 2023 with the second section to Century City in 2025, and the third and final section to the Westwood/VA Hospital in 2026. When complete, the Purple Line will speed transit riders between downtown L.A. and Westwood in 25 minutes, with other stations at Wilshire/Rodeo in Beverly Hills, Century City/Constellation in Century City, and Westwood/UCLA and the Westwood/VA Hospital in Westwood. The subway extension is projected to serve 59,000 riders daily — including 17,000 new riders.

“The Purple Line Extension Project is an important part of Metro’s ambitious plan to improve and expand mobility throughout Los Angeles County and will serve our region’s second-largest job center,” said Metro CEO Phillip A. Washington. “This is one of the most significant transit projects we plan to deliver to the public before the Summer Olympic and Paralympic games arrive in Los Angeles in 2028.”

View comments or post a comment on this story. (0 Comments)

More News

New Metra railcar RFP allows for alternative designs

Proposals will be due in August and Metra hopes to finalize a deal by the end of the year for at least 200 new cars.

Sonoma-Marin rail system carries 100,000th bicyclist

Since opening its doors in 2017, SMART passengers have included bicyclists who use their bikes to get to and from stations on a regular basis.

Alstom opens online marketplace for mobility sector

StationOne connects professionals in the railway industry and is designed as an efficient way to both promote and access the broadest possible range of products and services.

LAX breaks ground on automated people mover

Once completed in 2023, the APM will connect with L.A. Metro's light rail system.

MBTA opens $17M rail station on schedule, on budget

The Blue Hill Avenue Station marks the completion of the Fairmount Commuter Rail Line.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation