Sound Transit's Hilltop Tacoma Link extension places first rail set

Posted on June 19, 2019

Crews work on sections of rail for the Hilltop Tacoma Link extension.
Sound Transit
Crews work on sections of rail for the Hilltop Tacoma Link extension.
Sound Transit

Crews on Sound Transit’s Hilltop Tacoma Link Extension project installed the first 300-foot rail segments for the 2.4-mile extension through the Stadium District and Hilltop neighborhood. The new rails were placed on Stadium Way south of Division Street. Once the rail installation is complete, there is two-week test and inspection period to ensure the rails meet design specifications.

The Hilltop Tacoma Link Extension is being built by Walsh Construction Company II LLC.

Since last fall, construction has concentrated on relocating underground utilities, building foundations for Link power poles, building traction power substations, and expanding the Link Operations and Maintenance facility near Freighthouse Square.

Initial work on the Hilltop Tacoma Link Extension includes relocating nearly 10,000 feet of underground utility lines and built the foundations for 60 of the more that 300 Link power poles that will be built as part of the project. At the Operations and Maintenance facility expansion nearly 200 piles have been installed and 50% of the utility work is complete. Crews will erect structural steel beams at the facility this July.

When finished, the project extends the existing Tacoma Link system up Stadium Way, N. E St., 1st Street, Division Avenue, and down Martin Luther King Jr. Way to South 19th Street. This includes relocating the existing Theatre District station and building seven new stations along the Link system.

Sound Transit is simultaneously working to extend regional light rail north, south, east and west, opening new stations every few years to form a 116-mile regional system by 2041. Northgate Link will open in 2021, to be followed in 2023 by the opening of service to Mercer Island, Bellevue and Redmond’s Overlake community.

Additional extensions to Shoreline, Mountlake Terrace, Lynnwood, Kent/Des Moines, Federal Way and downtown Redmond are planned in 2024. Further light rail extensions are scheduled to reach West Seattle, Fife and Tacoma in 2030; Ballard in 2035; Paine Field and Everett in 2036; and South Kirkland and Issaquah in 2041.

View comments or post a comment on this story. (1 Comment)

More News

NJ TRANSIT submits revised financial plan for Portal North Bridge Project

The moves comes after feedback from FTA and U.S. DOT on a previous submission, making more local money available for the project while keeping costs in check. 

MBTA begins replacement of Chelsea Commuter Rail Station

Serving the Newburyport/Rockport Commuter Rail Line, the current station is inconvenient for transfers to other modes of service.

Metra will hold fares steady, budget $2.6B for capital improvements

As it does every year, the agency searched for ways to control or reduce its operating costs to head off the need for a fare increase.

LIRR rolls out newest fleet of railcars

The new cars incorporate and improve upon the most successful and popular features of the MTA’s two recent electric car fleets.

Sound Transit breaks ground on light rail extension

The $2.9 billion project budget includes up to $1.17 billion from a Full Funding Grant Agreement executed by the FTA.

See More News

Post a Comment

Post Comment

Comments (1)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation