Security and Safety

PTC now operating on 48K plus miles, according to FRA report

Posted on May 29, 2019

All railroads have committed to fully implementing PTC on their required main lines by Dec. 31, 2020.
Metrolink
All railroads have committed to fully implementing PTC on their required main lines by Dec. 31, 2020.
Metrolink

The Federal Railroad Administration (FRA) released a status update reflecting railroads’ self-reported progress toward fully implementing positive train control (PTC) systems as required by Congress.

Based upon railroad’s First Quarter 2019 PTC Progress Reports submitted to FRA by April 30, those required to implement PTC continue to make significant progress toward its full implementation on the required main lines. As of March 31, PTC systems were in operation on almost 48,050 of the nearly 58,000 route miles subject to the statutory mandate — a 3% increase from last quarter. Also, railroads are conducting advanced field testing, known as revenue service demonstration (RSD), on an additional 341 route miles.

With approximately 19 months remaining until the statutory implementation deadline, FRA continues to conduct comprehensive and vigorous regulatory oversight of railroad efforts to meet it. It is doing so by providing technical assistance to all host and tenant railroads, and coordinating with PTC system component suppliers and vendors.

  • All 41 railroads subject to the statutory mandate complied with the law by either fully implementing a PTC system by Dec. 31, 2018, or demonstrating they qualified for FRA approval of an alternative schedule, permitting up to two additional years to finish fully implementing PTC systems on all their required main lines.
  • Specifically, four railroads had fully installed PTC and 37 others sufficiently demonstrated they met or exceeded the six statutory criteria necessary to qualify for an alternative schedule.
  • All railroads have committed to fully implementing PTC on their required main lines by Dec. 31, 2020.

With all necessary PTC system hardware installed, spectrum acquired, and testing having been initiated, the key remaining steps for full implementation include: (1) conducting RSD of uncertified PTC systems on the general rail network; (2) submitting a PTC Safety Plan and obtaining PTC System Certification from FRA (host railroads only); (3) achieving interoperability between host railroads and tenant railroads; and (4) activating the PTC system so it governs all operations on the required main lines. FRA has also developed a new set of graphics to track railroad progress, focusing on each of these significant remaining elements of full implementation.

A key requirement of the original statutory mandate is interoperability, meaning the controlling locomotives and cab cars of any host railroad and tenant railroad operating on the same main line will communicate with and respond to the PTC system, including uninterrupted movements over property boundaries.

In April, FRA sent a letter to each freight, non-Class I tenant railroad that operates on at least one main line subject to the mandate, emphasizing the importance of timely implementation, and inviting them to meet with FRA in Washington, D.C., this summer. FRA plans to meet individually with each tenant railroad to offer technical assistance with respect to PTC system implementation. On June 5, FRA will host the second PTC Collaboration Session to share best practices with industry and jointly address any challenges.

View comments or post a comment on this story. (0 Comments)

More News

MTA to add 500 officers to NYCT to bolster safety, stem fare evasion

From 2013 to 2017, assaults reported by workers increased 15.2%, and lost revenue increased from $105M in 2015 to $225M in 2018.

HART, union agree to add driver safety barriers

The agency allocated $1 million toward the project with each installed barrier estimated to cost $5,000.

PSTA fast tracks new safety barriers to protect bus drivers

Planned safety upgrades come less than three weeks after HART bus driver Thomas Dunn was murdered on the job by a passenger.

BART police taking new steps to combat cellphone thefts

BART had 402 electronic item thefts reported in the system from January 1st through last month.

Inadequate planning, insufficient training led to Amtrak derailment

In December 2017, Amtrak Cascades train 501 derailed on an overpass as it entered a 30-mph curve at approximately 78 mph.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation