S.F. MTA to award $233.5M subway contract
A construction approach called "deep tunneling" will be used to construct the Central Subway. Deep tunneling allows most of the work to be done below ground, reducing disruption on the surface by using the TBMs, a technology that has been used extensively throughout the world.
San Francisco Municipal Transportation Agency (SFMTA), which oversees all surface transportation in the city, including the Municipal Railway (Muni), announced the initial notice to proceed (NTP) authorization for the Central Subway's largest construction contract, $233.5 million, will be issued this week.
The SFMTA will move forward with the first of three NTP authorizations for the tunneling contract, awarded in June. This NTP allows the contractor to proceed with ordering the two tunnel boring machines (TBM) needed to construct the twin bore tunnels for the underground portion of the Central Subway Project.
The contract has three distinct NTP authorizations: NTP 1 ($35M) authorizes procurement of the TBMs; NTP 2 ($36M) authorizes construction of the tunnel launch box and contractor's work area; and NTP 3 ($163M) authorizes commencement of tunneling, which includes construction of approximately 8,240-foot-long precast concrete segmental lined twin-bored guideway tunnels, construction of five emergency cross passages between bored tunnels and construction of station end walls.
A construction approach called "deep tunneling" will be used to construct the Central Subway. Deep tunneling allows most of the work to be done below ground, reducing disruption on the surface by using the TBMs, a technology that has been used extensively throughout the world. Deep tunneling has great potential for controlling project costs by minimizing surface construction staging, reducing utility relocations and shortening construction time.
The only visible tunneling activity will occur at the portal construction location (4th Street between Bryant and Harrison streets) and at the excavation site (Columbus Avenue at Union Street).
The second utility relocation contract began this spring and is underway on Stockton Street to prepare for construction of the Union Square/Market Street Station.
Central Subway business outreach, conducted at more than 60 events and in collaboration with nearly 50 partners, has resulted in more than $115 million in contract awards combined for local, disadvantaged or small business enterprises (SBE) to date. In fact, six of the 11 prime contractors working on the Central Subway Project are certified as SBE, DBE or LBE.
Thus far, the project will bring in nearly $90 million to local businesses and create thousands of job opportunities.
More Rail

New York MTA Advances Final Contract for Second Avenue Subway Expansion
Contract Four is the largest in the Second Avenue Subway Phase 2 project and includes construction of station infrastructure, tracks, and signals for the subway expansion, MTA officials said. Work on Contract Four will begin in 2027.
Read More →
San Diego MTS Breaks Monthly Trolley Ridership Record
Agency officials said July’s ridership indicates MTS’s continued recovery from the pandemic.
Read More →
Report Examines NJ TRANSIT Reliability, Funding Challenges
The Garden State Initiative analysis examines the roles of Amtrak infrastructure, fleet management, and agency operations while recommending a more performance-based approach to improving reliability.
Read More →
Stadler, CapMetro Sign Long-Term Rail Fleet Support Agreement
Beginning in 2027, Stadler will provide on-site technical expertise, spare parts support, training, and obsolescence management to help extend the reliability and longevity of CapMetro’s GTW fleet.
Read More →
Biz Briefs: Alstom Lands Canadian Contract, LYT to Supply California TSP, and More
In METRO's latest installment, we take a look at recent news from Complete Coach Works, Beep, FlixBus, and more partnerships making headlines across the transportation sector.
Read More →
CATS Gold Line Marks 5 Years of Service, 2.8M Passenger Trips
With a six-mile expansion planned, the Charlotte streetcar is positioned to connect more neighborhoods and major transit hubs across the region.
Read More →
Why Simulating Pedestrian Movement Has Become Essential for Modern Rail Stations
Pedestrian microsimulation is helping rail planners identify bottlenecks, test station designs, and prepare complex transit hubs for growing passenger volumes.
Read More →
Amtrak Begins Major Construction at New York’s Sunnyside Yard
The new maintenance facility will support Amtrak’s Airo trainsets while improving maintenance efficiency and turnaround times in New York.
Read More →
Chicago Leaders Unveil Plans for O’Hare Airport Express Train
The privately developed project would offer a 15-minute trip between downtown and O’Hare’s Terminal 2, with trains operating every 15 minutes on a dedicated track. The service would use battery-electric trains and three existing freight rail rights-of-way.
Read More →
OCTA Maps Out 30-Year Strategy to Protect Coastal Rail Corridor
The draft feasibility report identifies strategies to protect the coastal rail line for decades as the agency continues near-term stabilization and sand placement efforts.
Read More →