Long Beach Transit, BYD mutually terminate electric bus contract

The FTA had earlier notified LBT that BYD submitted an invalid DBE certification during the procurement process leading to the original April 29, 2013 agreement, and that the contract between LBT and BYD Motors Inc. was therefore not eligible for federal funding.

March 27, 2014
Long Beach Transit, BYD mutually terminate electric bus contract

 

2 min to read


California-based Long Beach Public Transportation Company (LBT) agreed Thursday to mutually terminate an agreement with electric bus manufacturer BYD Motors Inc. to build battery-operated electric buses for the transit company.

Obtaining financial assistance from the Federal Transit Administration (FTA) for the $12.1 million project was an essential component of the agreement. The FTA had earlier notified LBT that BYD Motors submitted an invalid Disadvantaged Business Enterprise (DBE) certification during the procurement process leading to the original April 29, 2013 agreement, and that the contract between LBT and BYD Motors Inc. was therefore not eligible for federal funding.

“LBT and BYD agreed to mutually terminate the contract to expeditiously resolve the issue. LBT has been cooperating with the FTA and working together with BYD in an effort to move forward amicably,” said Kenneth McDonald, president/CEO of LBT.

Terms of the mutual termination agreement provide that neither LBT nor BYD will take legal actions against one another.

“The action the Board has taken today to mutually terminate the contract enables us to look ahead at the possibility of a new RFP in the coming months to bring the City of Long Beach clean-running zero-emission public buses,” said Long Beach Transit Board Chair, Freda Hinsche Otto.

Transit Investments for Greenhouse Gas and Energy Reduction (TIGGER) program funds are still available to LBT for a new contract. Transit officials expect to evaluate a competitive rebid of the project. Subsequently, a new RFP and review process would follow.

More Bus

paratransit bus
SponsoredMarch 16, 2026

Measuring the True Cost of Paratransit Fleets

What truly drives the cost of a paratransit fleet? Beyond the purchase price, seven operational factors quietly determine maintenance frequency, downtime, and long-term service reliability. This whitepaper explores how these factors shape lifecycle cost and what agencies should evaluate when selecting paratransit vehicles.

Read More →
Cover photo for METROspectives with The Bus Coalition
Busby Alex RomanMarch 13, 2026

Inside The Bus Coalition’s Push for Stronger Federal Transit Investment

In this conversation, TBC’s Executive Director Ed Redfern, President Corey Aldridge, and Washington Representative Joel Rubin outline the coalition’s key policy priorities, the challenges facing transit agencies, and how industry stakeholders can work together to strengthen the voice of bus transit at the federal level.

Read More →
Cover photo for Biz Briefs dated March 6, 2026
Technologyby Staff and News ReportsMarch 6, 2026

Biz Briefs: Tolar Manufacturing Supports PSTA Spark Service and More

Stay informed with these quick takes on the projects and companies driving progress across the transportation landscape.

Read More →
Ad Loading...
Passengers boarding a PRT bus
Busby StaffMarch 2, 2026

Pittsburgh Unveils 'Bus Line Refresh' Plan

Originally introduced in 2023 as the Bus Line Redesign, the effort has evolved into a more targeted update that maintains familiar routes while improving reliability, frequency, evening and weekend service, and connections across Allegheny County.

Read More →
Stickers and a paper bus for S3 bus line
Busby StaffMarch 2, 2026

Seattle's Sound Transit Breaks Ground on S3 Bus Line

S3 will connect communities along SR 522 with fast, reliable, battery-electric bus service from Shoreline South Station to Bothell via Kenmore and Lake Forest Park. 

Read More →
PRT bus stop with articulated bus.
Busby StaffFebruary 20, 2026

Pittsburgh Regional Transit Announces All-Door Boarding on the University Line

All-door boarding will allow passengers to pay while entering the front, middle, or rear doors of the University Line’s 60-foot articulated buses.

Read More →
Ad Loading...
Patrick Scully, president at Complete Coach Works.
Managementby StaffFebruary 18, 2026

Complete Coach Works Names Patrick Scully President

He succeeds the company founder, Dale Carson, who remains chairman of the board. 

Read More →
A MARTA articulated bus.
Busby StaffFebruary 13, 2026

Atlanta's MARTA Sets Date for 'A-Line' BRT Launch

The five-mile Rapid A-Line connects Downtown Atlanta to Capitol Gateway, Summerhill, Peoplestown, and the Beltline’s Southside Trail.

Read More →
A Picture of Ster Seating's Parent/Child transit seating product.
Technologyby StaffFebruary 10, 2026

Ster Seating, Maryland Transit Launch First Parent/Child Transit Seat in North America

The configuration uses Ster Seating's Gemini seat platform to create a family-friendly floor layout specifically engineered to accommodate parents traveling with young children.

Read More →
Ad Loading...
Rendering of Sound Transit's Renton Transit Center
Busby StaffFebruary 5, 2026

Seattle’s Sound Transit Breaks Ground on New Transit Center

The Renton Transit Center project will relocate and rebuild the Renton Transit Center to better serve the regional Stride S1 line, local King County Metro services, and the future RapidRide I Line.

Read More →