Sound Transit completes first phase of University Link testing

Posted on June 25, 2015

SounderBruce
SounderBruce

Sound Transit contractors have completed initial work to integrate and test Seattle’s University Link light rail signal and power systems as part of the push to open the extension in early 2016.

Over the past several months Sound Transit contractors have installed and tested new power, safety, train control and communications systems in most of the 3.1 miles of tunnels between Westlake Station in downtown Seattle and the University of Washington.

The work included installing and testing new light rail control and safety systems for the entire light rail line. Workers also energized the new overhead lines in the University Link tunnels that power the trains.

The $1.8 billion University Link light rail extension includes new stations at Capitol Hill and the University of Washington. The line is entirely underground and currently $150 million under budget and six to nine months ahead of schedule. A trip from UW to downtown will take eight minutes bypassing some of the most congested traffic in the region.

Over the next months, contractors will remove the temporary wall and doors between the Downtown Seattle Transit Tunnel (DSTT) and the University Link tunnels and install the last 600-feet of power and communication lines in that section.

During the final phases of testing beginning this fall, all trains that operate during normal service hours will continue on to Capitol Hill and UW Station before returning south. All northbound passengers will still have to de-board at Westlake Station and the first station southbound will still be Westlake until the extension opens in early 2016.

This final phase, also called "pre-revenue service testing," is necessary to familiarize operators with the new stations and ensure all systems are performing well.

University Link light rail train testing from Sound Transit Video on Vimeo.

View comments or post a comment on this story. (0 Comments)

More News

The Boring Co. chosen to build Chicago Express Service

Plans to deliver 12-minute service from Downtown to O’Hare Airport using electric vehicles in underground tunnels.

Siemens unveils new Velaro high-speed train

Running at about 186 miles per hour, the new high-speed train uses 30% less energy than previous Velaro models, which translates to average savings of 1,375 tons of CO2 a year.

As China's rail transit systems boom, public-private partnerships face reckoning

The results have not always been positive, as cities grapple with inexperienced state-owned companies and inadequate risk management overrides prudent accounting.

Oregon's Safety Oversight Program receives FTA certification

States must receive FTA certification by April 15, 2019 or new federal transit funds cannot be awarded.

APTA names winners of 2018 rail safety, security 'excellence' awards

The awards recognize public transportation organizations for their innovative and proactive safety and security programs.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close