Sound Transit completes first phase of University Link testing

Posted on June 25, 2015


Sound Transit contractors have completed initial work to integrate and test Seattle’s University Link light rail signal and power systems as part of the push to open the extension in early 2016.

Over the past several months Sound Transit contractors have installed and tested new power, safety, train control and communications systems in most of the 3.1 miles of tunnels between Westlake Station in downtown Seattle and the University of Washington.

The work included installing and testing new light rail control and safety systems for the entire light rail line. Workers also energized the new overhead lines in the University Link tunnels that power the trains.

The $1.8 billion University Link light rail extension includes new stations at Capitol Hill and the University of Washington. The line is entirely underground and currently $150 million under budget and six to nine months ahead of schedule. A trip from UW to downtown will take eight minutes bypassing some of the most congested traffic in the region.

Over the next months, contractors will remove the temporary wall and doors between the Downtown Seattle Transit Tunnel (DSTT) and the University Link tunnels and install the last 600-feet of power and communication lines in that section.

During the final phases of testing beginning this fall, all trains that operate during normal service hours will continue on to Capitol Hill and UW Station before returning south. All northbound passengers will still have to de-board at Westlake Station and the first station southbound will still be Westlake until the extension opens in early 2016.

This final phase, also called "pre-revenue service testing," is necessary to familiarize operators with the new stations and ensure all systems are performing well.

University Link light rail train testing from Sound Transit Video on Vimeo.

View comments or post a comment on this story. (0 Comments)

More News

Siemens, partners deliver automated peoplemover for Frankfurt Airport

The company will deliver 12 fully automated two-car trains equipped with GoA4 Communication Based Train Control Trainguard MT CBTC, the track work equipment, the station platform doors, communication system, depot equipment, and the power supply system.

FRA taking proactive approach to help railroads meet PTC requirement

At the direction of Secretary Elaine L. Chao, the FRA is taking a proactive approach to ensure railroads acquire, install, test, and fully implement certified PTC systems in time to meet the congressional interim deadline of Dec. 31, 2018.

Despite federal uncertainty, N.C. light rail project optimistic about funding

Half of the Durham-Orange light rail’s cost — totaling over a billion dollars — is expected to come from the federal government.

Las Vegas Monorail unveils Google Pay mobile ticketing

The Monorail now offers riders the ability to quickly and easily purchase fares online and use their phone at the fare gates for immediate transit access to everything along the Las Vegas Strip.

Charlotte Area Transit launches LYNX Blue Line extension

The 9.3-mile extension, coined the Blue Line Extension (BLE) during construction, continues the alignment north from the previous terminus stop at 7th Street Station and now culminates at UNC Charlotte’s main campus.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment



Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close