Rail

Sound Transit completes first phase of University Link testing

Posted on June 25, 2015

SounderBruce
SounderBruce

Sound Transit contractors have completed initial work to integrate and test Seattle’s University Link light rail signal and power systems as part of the push to open the extension in early 2016.

Over the past several months Sound Transit contractors have installed and tested new power, safety, train control and communications systems in most of the 3.1 miles of tunnels between Westlake Station in downtown Seattle and the University of Washington.

The work included installing and testing new light rail control and safety systems for the entire light rail line. Workers also energized the new overhead lines in the University Link tunnels that power the trains.

The $1.8 billion University Link light rail extension includes new stations at Capitol Hill and the University of Washington. The line is entirely underground and currently $150 million under budget and six to nine months ahead of schedule. A trip from UW to downtown will take eight minutes bypassing some of the most congested traffic in the region.

Over the next months, contractors will remove the temporary wall and doors between the Downtown Seattle Transit Tunnel (DSTT) and the University Link tunnels and install the last 600-feet of power and communication lines in that section.

During the final phases of testing beginning this fall, all trains that operate during normal service hours will continue on to Capitol Hill and UW Station before returning south. All northbound passengers will still have to de-board at Westlake Station and the first station southbound will still be Westlake until the extension opens in early 2016.

This final phase, also called "pre-revenue service testing," is necessary to familiarize operators with the new stations and ensure all systems are performing well.

University Link light rail train testing from Sound Transit Video on Vimeo.

View comments or post a comment on this story. (0 Comments)

More News

Feds wants more proof of local money for Durham-Orange light rail line

Go Triangle expects its Board of Trustees to vote April 26 on a $70 million engineering contract, which would be executed only after the FTA allows the project to advance.

SEPTA trains collide, injuring 4

Crews are still working to remove the 18 cars involved, with each car weighing about 37 tons. The NTSB is on the scene and fully in charge of the investigation.

Minn. legislators attempting to move $900M from rail to roads, bridges

GOP legislators have long sought to block planning and funding for light-rail projects, saying they put metro-area priorities above rural Minnesota.

Alstom secures $105M Australian trainset contract

The contract will expand PTV’s fleet to 101 trains (606 cars) delivered from Alstom’s manufacturing facility in Ballarat since 2002.

DC Streetcar fares to remain free

The decision to hold off on charging fares was based on two reasons — District Department of Transportation feared charging even $1 per ride would scare away passengers and charging a fare would actually cost the District money.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The number 1 resource for vocational truck fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close