FRA report finds most railroads will miss PTC deadline
The report is mandated by the House of Representatives Appropriations Committee and shows that after seven years and significant assistance from FRA, most railroads will miss the Dec. 31, 2015 implementation deadline that Congress established in 2008.
The Federal Railroad Administration (FRA) sent its “Status of Positive Train Control Implementation” report to Congress. The report is mandated by the House of Representatives Appropriations Committee and shows that after seven years and significant assistance from FRA, most railroads will miss the Dec. 31, 2015 positive train control (PTC) implementation deadline that Congress established in 2008.
“Positive Train Control is the most significant advancement in rail safety technology in more than a century. Simply put: it prevents accidents and saves lives, which is exactly what we seek to do at The Department of Transportation every single day. We will continue to do everything in our power to help railroads install this technology,” U.S. Transportation Secretary Anthony Foxx said.
Ad Loading...
The National Transportation Safety Board (NTSB) began calling for train control systems like PTC in 1969, and FRA was involved in establishing PTC standards with stakeholders for more than a decade before the 2008 mandate. Three years before Congress passed the PTC mandate, FRA issued its final rule that established uniform PTC standards for railroads willing to voluntarily install the technology.
PTC prevents train-to-train collisions, over-speed derailments, incursions into established work zone limits and a train going to the wrong track because a switch was left in the wrong position.
In 2008, Congress passed the Rail Safety Improvement Act (RSIA), requiring all Class I railroads transporting poisonous-by-inhalation hazardous (PIH) or toxic-by-inhalation hazardous (TIH) materials and all railroads providing passenger service to implement Positive Train Control by Dec. 31, 2015.
FRA has provided significant assistance and support to railroads in order to help them become PTC compliant. Those efforts include:
Providing more than $650 million to passenger railroads, including nearly $400 million in Recovery Act funding.
Ad Loading...
Issuing a nearly $1 billion loan to the Metropolitan Transportation Authority to implement PTC on the Long Island Rail Road and Metro-North.
Building a PTC test bed in Pueblo, Colo.
Working directly with the Federal Communications Commission and the Advisory Council on Historic Preservation to resolve issues related to spectrum use and improve the approval process for PTC communication towers.
Dedicating staff to continue work on PTC implementation in March 2010, including establishing a PTC task force.
APTA President/CEO Michael Melaniphy released the following statement:
"The commuter rail industry is 100 percent committed to developing and installing positive train control (PTC) technology. Despite the commuter rail industry's best efforts, implementing PTC nationwide by the end of this year is not possible. This was never a realistic deadline because of the significant challenges — technology, spectrum, and funding — that still remain to successfully and safely implement PTC.
"It is important to note that when Congress passed the 2008 Rail Safety Improvement Act and mandated PTC, the technology available then was not mature and did not meet all the requirements of the statute.
"In addition, as explained in the new Federal Railroad Administration report, commuter rail systems have had a significant challenge in acquiring radio spectrum. PTC is a communications intense technology which requires radio spectrum to transmit data between trains and communications towers. APTA has asked the Federal Communications Commission to allocate free spectrum for commuter railroads as a public safety priority, but so far, it has refused to do so. Congress can solve this problem by directing the FCC to make the necessary spectrum available.
"Last but not least, the commuter rail industry has already spent $950 million on PTC implementation and conservative estimates are that $3.48 billion is needed to complete implementation nationwide. Currently, Congress has only appropriated $50 million for this critical federal safety technology."
Amtrak will open grant applications March 23 for community projects near the Frederick Douglass Tunnel alignment in Baltimore as part of a $50 million investment tied to the B&P Tunnel Replacement Program.
The Denmark Station $2.3 million construction investment project includes a new 280-foot concrete boarding platform, built eight inches above the top of rail, for improved accessibility for passengers with disabilities and families with small children and much more.
Caltrain and its partners have implemented safety improvements at specific locations in response to known risk conditions, operational needs, and available funding since the agency’s founding.
On a recent episode of METROspectives, METRO Magazine’s Executive Editor Alex Roman sat down with Ana-Maria Tomlinson, Director of Strategic & Cross-Sector Programs at the CSA Group, to explore a bold initiative aimed at addressing those challenges: the development of a National Code for Transit and Passenger Rail Systems in Canada.
Competitive FTA grants will support accessibility upgrades, family-friendly improvements, and cost-efficient capital projects at some of the nation’s oldest and busiest transit hubs.
The 3.92-mile addition will soon take riders west beyond its current Wilshire and Western station in Koreatown, continuing under Wilshire Boulevard through neighborhoods and communities including Hancock Park, Windsor Square, the Fairfax District, and Carthay Circle into Beverly Hills.
Under the plan, all long-distance routes will transition to a universal single-level fleet, replacing today’s mix of bi-level and single-level equipment.