Tunnel boring work set to begin for L.A. Metro rail extension
STV is serving as the engineer-of-record and principal design firm for the 2.6-mile-long Purple Line extension.

Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026.
L.A. Metro

Two state-of-the-art tunnel boring machines (TBMs) will soon begin work on Section 2 of the Los Angeles County Metropolitan Transportation Authority’s (Metro) Purple Line Project, aided by the engineering and design services provided by STV, a transportation and infrastructure firm.
Working as part of the design-build team led by Tutor Perini and O&G Industries, STV is serving as the engineer-of-record and principal design firm for the 2.6-mile-long Purple Line Section 2 extension that will link Section 1 running through the Miracle Mile District with Section 3 connecting Century City to Westwood. Overall, the $6.3 billion Purple Line extension will run 9.1 miles from Koreatown to Westwood.
STV’s services include the design of stations at Beverly Hills and Century City along with the running tunnels. The firm also engineered and designed the so-called “launch box” in Century City where the two 400-foot-long TBMs will be lowered into excavations extending more than 70 feet below Constellation Boulevard to begin their 14- month journeys.
The construction of the Beverly Hills and Century City stations will use a cut-and-cover method to build entrances, platforms, and concourses along with additional space for power, ventilation systems, and communications. STV will also be providing engineering and design services for the trackwork, traction power, train control, and communications systems.
Section 1 of the Purple Line is nearly a third complete and is scheduled to open in 2023. Section 2 is expected to be completed by 2025 with Section 3 scheduled to open shortly after in 2026. Once completed, the subway ride from downtown Los Angeles to Westwood is expected to take about 25 minutes.
More Rail

New York MTA Leverages Zoning Program to Advance Station Accessibility
Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.
Read More →
Virginia's $28.5B Transportation Plan Targets Transit and Rail
Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.
Read More →
DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades
Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.
Read More →
D Line Expansion Fuels Growth Across LA Metro's Rail System
Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.
Read More →
Southern California's Metrolink Debuts Contactless Fare Payment Pilot
Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.
Read More →
California's BART Approves FY27 Budget While Maintaining Service Levels
The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.
Read More →
Penn Station Transformation Advances with Design Unveiling
The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.
Read More →
Second Avenue Subway Phase 2 Advances into Major Construction Stage
New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.
Read More →
The Invisible Infrastructure of Passenger Flow
What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.
Read More →
Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures
The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.
Read More →