Streetcar Projects Continue Breaking Ground Despite Uncertain Federal Future

Federal officials look at new rules to make streetcars more eligible — but overall funding may be cut in budget battles.

by Cliff Henke
March 14, 2012
Streetcar Projects Continue Breaking Ground Despite Uncertain Federal Future

 

6 min to read


The progress of Cincinnati's streetcar project could be viewed as a microcosm of the re-emergence of the oldest mode of urban rail service.

After rejection of state funding by Ohio Gov. John Kasich as one of the first acts of his new administration, the ensuing re-scoping of the project and a defeat of a local ballot initiative to kill it completely, construction of the starter segment of the Cincinnati Streetcar is finally under way. The local water utility, Greater Cincinnati Water Works, is relocating the water mainline so that the shallow-trench track construction can begin.

Overcoming opposition
The project was much bigger at the time that the U.S. Department of Transportation (U.S. DOT) awarded the project a $25 million Urban Circulator grant in 2009, part of the FTA's, EPA's and U.S. Department of Housing and Urban Development's Liveability Initiative. Some observers believe that Gov. Kasich, elected in the conservative backlash that swept the 2010 elections, singled out the streetcar project for cuts because of its high profile in the Obama Administration's Livability policy. After all, it was given the highest rating of all transportation projects in the Buckeye State by a nonpartisan panel charged with evaluating projects for state funding.

Ad Loading...

However, it is also worth pointing out that the recently defeated referendum attempting to kill the project was also supported by the local chapter of the National Association for the Advancement of Colored People (NAACP), not exactly a right-wing interest group. The NAACP was against it due to some concerns about gentrification that might be brought about by the urban renewal that is expected to result.

Once the referendum was defeated, U.S. DOT officials supplemented the earlier Urban Circulator Grant with a Transportation Investment Generating Economic Recovery (TIGER) grant. This one was for $10.9 million. The rest of the $110 million project cost will be city municipal bond proceeds, some in-kind, and cash private sector contributions as well as a Congestion Mitigation and Air Quality grant from the federal highway program.

As with most modern streetcar projects, construction is proceeding one city block at a time and will be completed quickly, which generates a catalyst for economic development that is faster and often far greater than with other modes, according to several studies of streetcar systems in the U.S. Vehicular and pedestrian traffic will be maintained during construction in each block, because both a lane of traffic and the sidewalk remain open. Revenue service is anticipated to begin in 2014.

First segment
The first segment consists of five modern streetcars operating along a couplet (circulator route) configuration, comprising four miles of single track in one direction. This starter segment includes 18 stops. The schedule will involve 10-minute headways at morning and afternoon peaks and 20-minute headways during off-peak times. The operating schedule is 16 to 18 hours per day, seven days per week.

Future extensions will include a connection and circulator through Cincinnati's Uptown area, the region's second largest employment center and home to the University of Cincinnati, Cincinnati Children's Hospital and the Cincinnati Zoo.

Although the City of Cincinnati is the project sponsor and owner, the Southwest Ohio Regional Transit Authority (SORTA) will operate the system through an Intergovernmental Agreement. SORTA is also the FTA grantee that received the Urban Circulator grant and will manage both that and the other federal grants, including the TIGER grant and the flexible funds from the highway program being used to fund the first segment.

Ad Loading...

"From day one, the Cincinnati Streetcar has been the little engine that could, and I am so proud of the community and its leaders for standing up on behalf of this important project and shepherding it through to this critical milestone." says Secretary of Transportation Ray LaHood. "The story in Cincinnati is about a community coming together, setting its priorities, and not being dissuaded by the naysayers or those who don't want progress."

LaHood and others supporting streetcar projects do so as investments in the future of cities, accelerating development and revitalizing the urban core of cities that undertake them. They look to the billions of dollars in economic development accelerated around the streetcar lines built in such diverse places as Portland, Ore.; Seattle; Little Rock, Ark.; Kenosha, Wis.; and Tampa, Fla. Moreover, they also look at the attraction redeveloped urban neighborhoods have in a changing economy, particularly to young professionals desiring a more walkable, diverse lifestyle. Because of this latter point, many cities see streetcars and the attendant urban redevelopment strategies as part of their overall economic strategies to attract industries looking to hire younger, more educated populations.[PAGEBREAK]
Breaking ground
Cincinnati's streetcar is not the only such system breaking ground this year. The St. Louis Loop Trolley is another Urban Circulator grant recipient, and it will also do so this year. Project officials there also expect to open in 2014.

Seattle's second line, the 2.2-mile First Hill Streetcar, is another streetcar breaking ground in 2012, though it is scheduled to open a year earlier, in 2013. However, this line is funded entirely with local funds, part of the ST2 referendum that voters approved in 2008. The Emerald City's first modern streetcar line, the South Lake Union project, was also funded virtually entirely with nonfederal funds, save for a small federal earmark it got in the days when those were still politically possible in Congress.

In addition, Atlanta's 2.3-mile Downtown Streetcar, from Martin Luther King Jr. National Historic Site to Centennial Olympic Park also began construction. It is also scheduled for revenue openings next year.
Three other streetcar projects that benefitted from TIGER grants are Tucson's 3.9-mile Modern Streetcar from the University of Arizona's campus to Downtown Tucson; Salt Lake City Sugar House Streetcar (2-mile system); and the 2.5-mile French Quarter Expansion Project in New Orleans, from Canal Street to Esplanade Avenue. The Tucson and New Orleans projects are also expected to open next year, while the Sugar House Streetcar is slated for a 2014 debut.

Many other streetcar projects are in varying stages of development. They include a downtown streetcar in Los Angeles; a circulator service Tyson's Corner in Northern Virginia, another circulator in Providence, RI; two streetcar projects in Dallas; and streetcar projects in Ft. Lauderdale, Fla., and Santa Ana, Calif. In addition, four other projects in the greater Washington, D.C., area are in development, two in the District itself (part of a larger network that is envisioned) as well as two other projects just outside D.C. in the Northern Virginia suburbs of Arlington. While all of these will require some federal funding assistance, another, the project for downtown Oklahoma City, may be able to be funded entirely with local funds thanks to a referendum voters passed in the city in 2010.

Cloudy picture
Like most major capital investment projects in public transportation, the full expansion of streetcar investments throughout the country will require policies to fund them. Unfortunately, the highly divisive political climate in Washington, D.C., may actually eliminate all discretionary transit funding, let alone an expansion, if conservatives in the House of Representatives have their way. Many of them question the rationale for a federal role in urban transportation funding. Even the Urban Circulator Program, started by the FTA using the exempt projects section of existing law in the Major Capital Investment Program, is under threat in this climate. 

Subscribe to Our Newsletter

More Rail

An OCTA coastal rail line train.
Rail•by Staff and News Reports•November 24, 2026

OCTA Finalizes 30-Year Strategy to Protect Coastal Rail Corridor

The agency approved its coastal rail resiliency study and will begin developing projects to protect seven miles of railroad as emergency stabilization efforts continue.

A VIA CNG bus on the road
Management•by Alex Roman•November 20, 2026

VIA, MBTA Reach Pre-Pandemic Ridership Milestones as Transit Use Climbs

VIA surpasses three million monthly trips for the first time since 2020, while the MBTA tops one million average weekday trips as both agencies report continued ridership growth.

Darren Kettle CEO of Metrolink
Management•by Alex Roman•November 20, 2026

People Movement: Metrolink's Kettle Announces Retirement, Feakins to CEO at UZURV, and More

In this edition, we also cover recent appointments and announcements at King County Metro, SilverRide, and more, showcasing the individuals helping to shape the future of transportation.

Ad Loading...
TTC Line 5
Management•by Alex Roman•November 18, 2026

How Gen Z's Changing Mobility Habits Are Reshaping Public Transit

As younger generations embrace multimodal mobility over private vehicles, transit agencies can rethink station design, the passenger experience, and public transportation's role in building connected communities.

A rendering of Amtrak's Airo trainset
Rail•by Alex Roman•November 18, 2026

Amtrak Expands Airo Fleet with Eight Higher-Capacity Trainsets

The new 10-car trains, expected to enter service in 2031, will provide about 34% more seating capacity to meet growing demand on the Northeast Corridor.

APTA Warns Proposed FTA Guidance Could Delay Major Transit Projects
Management•by Alex Roman•November 18, 2026

APTA Urges FTA to Withdraw Proposed Capital Investment Grants Guidance

The association warns that proposed changes could delay transit projects, reduce federal funding, and create new hurdles for 47 projects currently in the CIG pipeline.

Ad Loading...
New Portal North Bridge Marks Major Milestone for Northeast Corridor Rail Service
Rail•by Alex Roman•November 17, 2026

Amtrak, NJ TRANSIT Launch Full Service on New Portal North Bridge

The completion of the two-track bridge over the Hackensack River eliminates a longstanding source of delays for NJ TRANSIT and Amtrak customers. It marks a major milestone for the Gateway Program.

A Metrolink station with two trains.
Rail•by Alex Roman•November 16, 2026

Southern California’s Metrolink Approves $508.8M Budget, Avoids Service Cuts

A $20 million state allocation allows the regional rail agency to maintain existing weekday and weekend service through fiscal year 2028, although longer-term funding challenges remain.

A wide shot of Alstom's Multilevel III commter railcar for NJ TRANSIT
Rail•by Alex Roman•November 13, 2026

NJ TRANSIT Approves $65.6M for Hudson-Bergen Light Rail Improvements

The funding marks the first phase of a planned $250 million investment over five years to modernize stations, overhaul vehicles, and improve system reliability and passenger safety.

Ad Loading...
STraffic's John Moon
Technology•by Alex Roman•November 12, 2026

STraffic Expands North American Presence with Fare Collection Technology

John Moon, Associate Director, Product Strategy at STraffic, discusses the company's growth in North America, its efforts to reduce fare evasion, and more.