SoCal Extension Breathes New Life Into Congested Corridor

The 91/Perris Valley Line is expected to replace thousands of vehicle trips along I-215 as well as I-15 and connecting State Route 91 and SR 60.

by By Richard Quirk, AIA
September 20, 2016
SoCal Extension Breathes New Life Into Congested Corridor

Images courtesy STV Inc.

4 min to read


Images courtesy STV Inc.

For the first time in more than 20 years, Southern California’s Metrolink commuter rail launched a new line into Riverside County, providing drivers in the heavily congested corridor a long-awaited alternative.

The new 91/Perris Valley Line began regular service in June — about 15 years after it was first proposed.

Ad Loading...

The new line, which parallels Interstate 215 along a 24-mile route from Riverside to Perris, features four new commuter stations, expanding access for thousands of new Metrolink riders along the I-215 corridor. The extension expands Metrolink service across 536 miles of the region and connects to three of its existing rail lines providing access to San Bernardino, Orange County and Los Angeles. This was accomplished by linking the Burlington Northern Santa Fe (BNSF) main line and the Riverside Downtown Station to the 21-mile San Jacinto Branch Line running south to Perris through a new 1,900-foot rail segment known as the Citrus Connection.

The 91/Perris Valley Line is expected to replace thousands of vehicle trips along I-215 as well as I-15 and connecting State Route 91 and SR 60.

In announcing the new service, Metrolink board Vice Chairman and Riverside County Transportation Commission (RCTC) member Daryl R. Busch, who also serves as mayor of Perris, hailed the extension as not only a way to ease congestion in the area, but as a means to spur economic growth. “There couldn’t be a better place for new train service,” said Busch. “This is a prime area for business and economic development and Metrolink will make it an even more attractive place to create jobs and transit-friendly housing.”


Projected growth
Current ridership on the line is projected to grow to more than 4,000 daily riders. Direct service between Union Station and South Perris takes a little over two hours to make the approximately 75-mile trip. Metrolink is currently offering discounted fares to help promote the service.

Ad Loading...

STV has been a partner with the RCTC since the 91/Perris Valley Line extension was first proposed in 2001, and was contracted by the commission to perform planning, environmental studies and reports, as well as the necessary engineering and construction support since the project broke ground in late 2013.

The extension was funded through federal, state and a special sales tax in Riverside County. It was one of the first projects to win funding under the Federal Transit Administration’s Small Starts program. STV helped prepare the documents, many of which have been used as templates for other Small Starts projects throughout the country.

“This extension will make a big difference in the quality of life for residents who want an alternative to sitting in traffic, and it also lays a strong foundation for economic development along the corridor,” said Therese McMillan, the acting administrator of the FTA at the time, who now serves as chief planning officer for the Los Angeles Metropolitan Transportation Agency.

Extensive Improvements
In addition to the four stations at Riverside-Hunter Park, Moreno Valley/March Field, Downtown Perris and South Perris, the new line required extensive improvements at existing grade crossings and culverts, installation of new traffic signals, the replacement of two bridges along the SJBL along the San Jacinto River, and the construction of communication towers and landscape and sound attenuation walls.

The new line was also praised by the American Planning Association’s Inland Empire Section, which recognized it with its Hard Won Victories Award. The award was given to the RCTC for its planning efforts in demonstrating how a plan can be developed and endorsed amid varying viewpoints.

Ad Loading...

The STV team designed the rail line’s four new stations in close collaboration with RCTC and Metrolink. Stations feature 510-foot-long platforms with canopies, ADA and safety amenities, including level boarding, ticket kiosks, scheduling information and parking ranging from about 450 to 900 cars. Built with flexibility and future expansion in mind, the stations accommodate platforms up to 850 feet long as well as double-tracking and second platforms in certain areas.

Safety Standards
In addition, STV worked with the RCTC and Metrolink to uphold stringent safety standards by replacing miles of worn track, upgrading multiple grade crossings and improving the line’s signal system, including design considerations for the implementation of Positive Train Control (PTC). Work also included designing a new layover facility for locomotive maintenance and inspection areas in South Perris.

The 91/Perris Valley Line extension is Metrolink’s first new expansion project since construction of the Antelope Valley Line in 1994. Since that time, STV has served as the general engineering consultant for the rail service, performing planning, engineering design, and program and construction management for various key assignments throughout the system’s development. Metrolink currently serves more than 44,000 daily riders, with more than 75% switching from cars to transit.

Richard Quirk, AIA is senior architect/project manager with STV Inc. (www.stvinc.com)

Subscribe to Our Newsletter

More Rail

MTA Advances Accessibility Improvements in Brooklyn
Paratransitby StaffJune 17, 2026

New York MTA Leverages Zoning Program to Advance Station Accessibility

Accessibility enhancements at Nevins St Station will be financed through a development agreement tied to the MTA's Zoning for Accessibility initiative.

Read More →
Six-Year Plan Boosts Virginia Transit, Rail Investments
Managementby StaffJune 17, 2026

Virginia's $28.5B Transportation Plan Targets Transit and Rail

Approved by the Commonwealth Transportation Board, the program supports ongoing infrastructure projects while providing new investments in transit, state of good repair and transportation alternatives.

Read More →
Security and Safetyby StaffJune 16, 2026

DOT: Brightline Corridor Incidents Fall 30% Following Federal Safety Upgrades

Safety improvements funded through a $25 million federal investment are credited with reducing trespassing and train-vehicle collisions along the Brightline Florida corridor.

Read More →
Ad Loading...
An LA Metro D Line train in Union Station
Managementby StaffJune 16, 2026

D Line Expansion Fuels Growth Across LA Metro's Rail System

Weekend rail ridership was especially strong, soaring 18% as riders embraced expanded access to jobs, entertainment, dining, and cultural destinations, said the agency. Total system ridership for May, including bus and rail, was 26,966,657.

Read More →
A user demonstrating Metrolink's contactless fare payment pilot.
Technologyby StaffJune 12, 2026

Southern California's Metrolink Debuts Contactless Fare Payment Pilot

Customers traveling between Redlands and Los Angeles can now tap their preferred payment method, including a credit or debit card, mobile wallet, or wearable device, at station validators before boarding and again while exiting.

Read More →
A BART train on the tracks.
Managementby StaffJune 12, 2026

California's BART Approves FY27 Budget While Maintaining Service Levels

The budget covers July 1, 2026, through June 30, 2027, a period when pandemic emergency funds run out, the District faces a structural deficit of $375 million, and a regional transit funding measure may appear on the November ballot.

Read More →
Ad Loading...
A rendering of the Amtrak New York Penn Station renovation
Railby StaffJune 9, 2026

Penn Station Transformation Advances with Design Unveiling

The historic redesign will transform the busiest transit hub in the Western Hemisphere from the tracks to the street level, creating a more efficient, cleaner, and functional experience for more than 600,000 daily commuters and millions of visitors.

Read More →
Groundbreaking event for Second Avenue Subway Phase 2 TBM construction.
Railby StaffJune 9, 2026

Second Avenue Subway Phase 2 Advances into Major Construction Stage

New York Governor Kathy Hochul joined leadership from the MTA, elected officials, and Harlem community leaders to break ground on the major construction stage of the transformative Second Avenue Subway Phase 2 project.

Read More →
A man sits in a passenger rail seat and looks at his phone.
Railby Elora HaynesJune 8, 2026

The Invisible Infrastructure of Passenger Flow

What a seat reservation system on Austria’s Railjet trains reveals about the future of rider experience, and why U.S. agencies should pay attention.

Read More →
Ad Loading...
Aerial view of Caltrain's electric service.
Railby StaffJune 5, 2026

Caltrain Board Approves FY27 Budget, Endorses Efficiency Measures

The move ensures Caltrain service will continue operating as usual in the near term, but long-term financial challenges remain for the rail agency absent a new revenue source.

Read More →