NYCT completes rail work via service initiative

Posted on January 17, 2012

For four consecutive weeknights hundreds of Metropolitan Transportation Authority New York City Transit (NYCT) workers labored through the late night and early morning hours cleaning, inspecting, repairing and replacing subway infrastructure on a nearly seven-mile segment of the normally busy Lexington Avenue Line.

NYCT's new FASTRACK initiative is an entirely new way to perform subway maintenance completely suspending train service over a segment of a subway line, giving workers uninterrupted access to tracks, signals, cables, lighting, third rail components and platform edges. During the four-night period, more than 300 vital tasks were completed — from rail replacement to roadbed cleaning to the scraping and painting of ceilings over tracks and platforms. Much of this work had not been performed in several years and some of it could only be done in the absence of trains over an extended period of time.

Three work trains supported nearly 70 work crews from several divisions within the Department of Subways. Work was performed in the stations along the line segment as well as the tunnels and even into the Joralemon Tube that connects Brooklyn to Manhattan.

In the planning for upwards of three months, the result was a seamless effort that saw maintenance workers specializing in different disciplines working to complete jobs and make improvements that customers would notice by the time service was resumed on the 4, 5 and 6 line for the next morning's rush period. Workers cleaned and replaced lighting fixtures, scraped dry mud from the roadbed while also removing trash and debris, as well as inspected and performed preventative maintenance on components crucial to providing safe and reliable service. They also scraped peeling paint from station ceilings and painted station areas. Rails were replaced in several areas along with a heavily utilized track switch just north of the Brooklyn Bridge Station.

Work also included inspections of equipment along the tracks; scraping and bagging of debris; replacement of tie and rail fastener plates; scraping and painting rubbing board and columns within station limits; cleaning of stations (mobile wash); cleaning of drains; and routine maintenance and performance testing of signals. All work was wrapped up and service restored to customers by 5:00 a.m. each morning.

View comments or post a comment on this story. (0 Comments)

More News

$8.2B invested along 20 miles of Valley Metro light rail

Economic development within one-half mile of the system has been stimulated by ridership that has exceeded original projections. Valley Metro began compiling development activity since construction started in 2005 as part of an economic development database.

Alstom to deliver 17 trains to Algeria

The Coradia Polyvalent for Algeria is a dual-mode train (diesel and electric, 25 kV) able to travel at speeds up to 99 mph. The train has six carriages and provides capacity for 265 passengers.

Fla.'s TriRail adds bike car

The new bike car contains 14 racks that will provide more room to maneuver bicycles on and off the train. A set of seats were removed from the lower level of the vehicle to make room for the bike racks.

Denver commuter rail maintenance facility Gold LEED certified

Sustainable features of the CRMF include efficient mechanics and lights for energy savings, water-efficient plumbing fixtures for reduction in water usage and specially designed windows that prevent thermal transfer.

US High Speed Rail launches TOD Institute, conference

Will work to increase the supply of new TODs and rail systems across America and will be holding a series of national and local events bringing together business and political leaders with planners and experts to advance knowledge sharing and project deal making.

See More News

Post a Comment

Post Comment

Comments (0)

More From The World's Largest Fleet Publisher

Automotive Fleet

The Car and truck fleet and leasing management magazine

Business Fleet

managing 10-50 company vehicles

Fleet Financials

Executive vehicle management

Government Fleet

managing public sector vehicles & equipment

TruckingInfo.com

THE COMMERCIAL TRUCK INDUSTRY’S MOST IN-DEPTH INFORMATION SOURCE

Work Truck Magazine

The resource for managers of class 1-7 truck Fleets

Schoolbus Fleet

Serving school transportation professionals in the U.S. and Canada

LCT Magazine

Global Resource For Limousine and Bus Transportation

Please sign in or register to .    Close